A piece of work can be completed in 18 days if A and B work together, in 24 days if B and C work together and in 36 days if A and C work together. The number of days required if all the three work together is
14
12
10
16
To solve the problem, we need to find out how many days A, B, and C will take to complete the work together based on the information given about their combined efficiencies.
1. Understanding the Work Rates:
- Let the total work be represented as 1 unit.
- If A and B can complete the work in 18 days, their combined work rate (efficiency) is:
Efficiency of A + B=118 units of work per day
2. Work Rate of B and C:
- If B and C can complete the work in 24 days, their combined work rate is:
Efficiency of B + C=124 units of work per day
3. Work Rate of A and C:
- If A and C can complete the work in 36 days, their combined work rate is:
Efficiency of A + C=136 units of work per day
4. Setting Up the Equations:
- Let the efficiencies of A, B, and C be represented as a,b,c respectively.
- From the above information, we can write the following equations:
a+b=118(1)
b+c=124(2)
a+c=136(3)
5. Adding the Equations:
- Adding equations (1), (2), and (3):
(a+b)+(b+c)+(a+c)=118+124+136
- This simplifies to:
2a+2b+2c=118+124+136
6. Finding a Common Denominator:
- The least common multiple (LCM) of 18, 24, and 36 is 72.
- Converting each fraction:
118=472,124=372,136=272
- Therefore:
2a+2b+2c=4+3+272=972=18
7. Finding the Combined Efficiency:
- Dividing both sides by 2:
a+b+c=116
8. Calculating the Time Taken by A, B, and C Together:
- If A, B, and C can complete 116 of the work in one day, the number of days required to complete the entire work is:
Days=1116=16 days
Final Answer:
The number of days required if all three work together is 16 days.
- Let the total work be represented as 1 unit.
- If A and B can complete the work in 18 days, their combined work rate (efficiency) is:
Efficiency of A + B=118 units of work per day
- If B and C can complete the work in 24 days, their combined work rate is:
Efficiency of B + C=124 units of work per day
- If A and C can complete the work in 36 days, their combined work rate is:
Efficiency of A + C=136 units of work per day
- Let the efficiencies of A, B, and C be represented as a,b,c respectively.
- From the above information, we can write the following equations:
a+b=118(1)
b+c=124(2)
a+c=136(3)
- Adding equations (1), (2), and (3):
(a+b)+(b+c)+(a+c)=118+124+136
- This simplifies to:
2a+2b+2c=118+124+136
- The least common multiple (LCM) of 18, 24, and 36 is 72.
- Converting each fraction:
118=472,124=372,136=272
- Therefore:
2a+2b+2c=4+3+272=972=18
- Dividing both sides by 2:
a+b+c=116
- If A, B, and C can complete 116 of the work in one day, the number of days required to complete the entire work is:
Days=1116=16 days
The number of days required if all three work together is 16 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
A334 daysB337 daysC5547 daysD449 days - Question 2 - Select One
A and B together can do a piece of work in 6 days . If A can alone do the work in 18 days then the number of days required for B to finsh the work is
A10B12C9D15 - Question 3 - Select One
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do the work in
A15B20C25D30
A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
View SolutionA and B together can complete a piece of work in 16 days while B and C together can complete the same work in 12 days and A and C together in 24 days. Find out the number of days that A will take to compete the work, working alone.
View SolutionA and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
View Solution