Doubtnut Promotions Sticky

A piece of work can be completed in 18 days if A and B work together, in 24 days if B and C work together and in 36 days if A and C work together. The number of days required if all the three work together is

A

14

B

12

C

10

D

16

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to find out how many days A, B, and C will take to complete the work together based on the information given about their combined efficiencies.

1. Understanding the Work Rates:
- Let the total work be represented as 1 unit.
- If A and B can complete the work in 18 days, their combined work rate (efficiency) is:
Efficiency of A + B=118 units of work per day

2. Work Rate of B and C:
- If B and C can complete the work in 24 days, their combined work rate is:
Efficiency of B + C=124 units of work per day

3. Work Rate of A and C:
- If A and C can complete the work in 36 days, their combined work rate is:
Efficiency of A + C=136 units of work per day

4. Setting Up the Equations:
- Let the efficiencies of A, B, and C be represented as a,b,c respectively.
- From the above information, we can write the following equations:
a+b=118(1)
b+c=124(2)
a+c=136(3)

5. Adding the Equations:
- Adding equations (1), (2), and (3):
(a+b)+(b+c)+(a+c)=118+124+136
- This simplifies to:
2a+2b+2c=118+124+136

6. Finding a Common Denominator:
- The least common multiple (LCM) of 18, 24, and 36 is 72.
- Converting each fraction:
118=472,124=372,136=272
- Therefore:
2a+2b+2c=4+3+272=972=18

7. Finding the Combined Efficiency:
- Dividing both sides by 2:
a+b+c=116

8. Calculating the Time Taken by A, B, and C Together:
- If A, B, and C can complete 116 of the work in one day, the number of days required to complete the entire work is:
Days=1116=16 days

Final Answer:
The number of days required if all three work together is 16 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :

    A334 days
    B337 days
    C5547 days
    D449 days
  • Question 2 - Select One

    A and B together can do a piece of work in 6 days . If A can alone do the work in 18 days then the number of days required for B to finsh the work is

    A10
    B12
    C9
    D15
  • Question 3 - Select One

    A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do the work in

    A15
    B20
    C25
    D30