Mukesh and Dinesh together can complete a work in 120 days. Mukesh alone can complete the work in 150 days. In how many days can Dinesh alone complete the work?
650
720
450
600
The correct Answer is:D
To find out how many days Dinesh alone can complete the work, we can follow these steps:
Step 1: Determine the work rates of Mukesh and Dinesh
- Mukesh and Dinesh together can complete the work in 120 days. Therefore, their combined work rate is:
Work rate of Mukesh + Dinesh=1120 work per day
- Mukesh alone can complete the work in 150 days. Therefore, Mukesh's work rate is:
Work rate of Mukesh=1150 work per day
Step 2: Calculate Dinesh's work rate
- Let Dinesh's work rate be 1d work per day, where d is the number of days Dinesh takes to complete the work alone.
- According to the work rates, we can set up the equation:
1150+1d=1120
Step 3: Solve for Dinesh's work rate
- Rearranging the equation gives:
1d=1120−1150
- To subtract the fractions, we need a common denominator. The least common multiple (LCM) of 120 and 150 is 600. Thus, we convert the fractions:
1120=5600,1150=4600
- Now substitute back into the equation:
1d=5600−4600=1600
Step 4: Find Dinesh's days to complete the work
- Taking the reciprocal gives:
d=600
- Therefore, Dinesh alone can complete the work in 600 days.
Final Answer:
Dinesh alone can complete the work in 600 days.
---
- Mukesh and Dinesh together can complete the work in 120 days. Therefore, their combined work rate is:
Work rate of Mukesh + Dinesh=1120 work per day
Work rate of Mukesh=1150 work per day
- Let Dinesh's work rate be 1d work per day, where d is the number of days Dinesh takes to complete the work alone.
- According to the work rates, we can set up the equation:
1150+1d=1120
- Rearranging the equation gives:
1d=1120−1150
- To subtract the fractions, we need a common denominator. The least common multiple (LCM) of 120 and 150 is 600. Thus, we convert the fractions:
1120=5600,1150=4600
- Now substitute back into the equation:
1d=5600−4600=1600
- Taking the reciprocal gives:
d=600
- Therefore, Dinesh alone can complete the work in 600 days.
Dinesh alone can complete the work in 600 days.
Similar Questions
Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?
View SolutionA and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 2 - Select One
U, V and W together can complete a work in 15 days. U alone can complete the work in 60 days. In how many days V and W together can complete the same work?
A10B20C14D12 - Question 3 - Select One
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
1 man and 1 woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days, can one woman alone complete the work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionX, Y and Z together can complete a work in 20 days. Y and Z can complete the same work in 30 days. In how many days X alone can complete the same work?
View SolutionP and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View Solution