Doubtnut Promotions Sticky

24 men can do work in X days and 32 women can do the same work in (X+8) days. The ratio of work done by 15 men and 12 women in the same time is 3:1.
In how many days, the work will be completed if 5 men and 4 women work together ?

A

24 days

B

18 days

C

36 days

D

48 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the logical sequence outlined in the video transcript.

Step 1: Define Variables
Let the efficiency of one man be m and the efficiency of one woman be w.

Step 2: Set Up the Work Ratio
According to the problem, the work done by 15 men and 12 women in the same time is in the ratio of 3:1. Therefore, we can write the equation:

15m12w=31

Step 3: Solve for the Ratio of Efficiencies
Cross-multiplying gives us:

15m=36w

This simplifies to:

mw=3615=125

Thus, if we assume w=5 (the efficiency of one woman), then m=12 (the efficiency of one man).

Step 4: Calculate Total Work for Men
Given that 24 men can complete the work in X days, the total work can be expressed as:

Total Work=24×m×X=24×12×X=288X

Step 5: Calculate Total Work for Women
Similarly, 32 women can complete the same work in X+8 days:

Total Work=32×w×(X+8)=32×5×(X+8)=160(X+8)

Step 6: Set the Total Work Equations Equal
Since both expressions represent the same total work, we can set them equal to each other:

288X=160(X+8)

Step 7: Solve for X
Expanding the right side:

288X=160X+1280

Now, rearranging gives:

288X160X=1280

128X=1280

Dividing both sides by 128:

X=10

Step 8: Calculate Total Work
Now substituting X back into the total work equation:

Total Work=288X=288×10=2880 units

Step 9: Calculate Efficiency of 5 Men and 4 Women
Now, we need to find the efficiency of 5 men and 4 women:

Efficiency of 5 men=5×m=5×12=60
Efficiency of 4 women=4×w=4×5=20

Thus, the total efficiency of 5 men and 4 women is:

Total Efficiency=60+20=80

Step 10: Calculate the Number of Days Required
Finally, the number of days required to complete the work is given by:

Days=Total WorkTotal Efficiency=288080=36

Final Answer
The work will be completed in 36 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 men can do work in X days and 32 women can do the same work in (X+8) days. The ratio of work done by 15 men and 12 women in the same time is 3:1.
    What is the value of X ?

    A15
    B10
    C12
    D18
  • Question 2 - Select One

    5 men can do a work in 6 days and 10 women can do the same work in 5 days. In how many days the work is done by 5 women and 3 men?

    A10 days
    B8 days
    C6 days
    D5 days
  • Question 3 - Select One

    12 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?

    A12
    B10
    C9
    D8