Doubtnut Promotions Sticky

It took 64 people 77 days to construct a house. What fraction of the work can be completed by 44 people in 96 days?

A

34

B

45

C

67

D

23

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will calculate the total work done by the first group of people and then determine how much work can be done by the second group of people. Finally, we will find the fraction of work completed.

Step 1: Calculate the total work done by 64 people in 77 days.
The total work can be calculated using the formula:
Total Work=Number of People×Number of Days
So, for 64 people working for 77 days:
Total Work=64×77

Step 2: Calculate the work done by 44 people in 96 days.
Using the same formula for the second group:
Work Done by 44 People=44×96

Step 3: Set up the fraction of work completed.
The fraction of work completed by 44 people in 96 days compared to the total work is given by:
Fraction of Work=Work Done by 44 PeopleTotal Work
Substituting the values from Steps 1 and 2:
Fraction of Work=44×9664×77

Step 4: Simplify the fraction.
We can simplify the fraction by canceling out common factors:
1. 44 and 64 can be simplified by dividing both by 4:
- 44÷4=11
- 64÷4=16

2. Now the fraction looks like:
11×9616×77

3. Next, we can simplify 96 and 16 by dividing both by 16:
- 96÷16=6

4. Now the fraction looks like:
11×677

5. Finally, simplify 11 and 77 by dividing both by 11:
- 77÷11=7

Now we have:
67

Final Answer:
The fraction of the work that can be completed by 44 people in 96 days is 67.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    How many workers are required for completing the construction work in the 10 days ?
    (i) 20% of the work can be completed by 8 workers in 8 days.
    (ii) 20 workers can complete the work in 16 days.
    (iii) One - eighth of the work can ve completed by 8 workers in 5 days.

    A(i) only
    B(ii) and (iii) only
    C(iii) only
    DAnyone of the three
  • Question 2 - Select One

    A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.

    A5511
    B4511
    C6411
    D6511
  • Question 3 - Select One

    A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?

    A12 days
    B8 days
    C9 days
    D1012 days