Joe complete 14 th of a task in 10 days , and Jack can complete 25 th of the same task in 9 days. How long will Joe and Jack take to complete the task working together ?
938 days
6110 days
1425 days
17 days
The correct Answer is:C
To solve the problem of how long Joe and Jack will take to complete the task working together, we can follow these steps:
Step 1: Determine Joe's total time to complete the task
Joe completes 14 of the task in 10 days. To find out how long it takes him to complete the entire task, we can set up the equation:
Total time for Joe=10 days×4=40 days
Step 2: Determine Jack's total time to complete the task
Jack completes 25 of the task in 9 days. To find out how long it takes him to complete the entire task, we can set up the equation:
Total time for Jack=9 days×52=452 days=22.5 days
Step 3: Calculate the work rates (efficiencies) of Joe and Jack
The work rate (efficiency) is calculated as the total work divided by the total time taken. Since the total work can be considered as 1 unit of work:
- Joe's efficiency:
Efficiency of Joe=1 work40 days=140 work/day
- Jack's efficiency:
Efficiency of Jack=1 work22.5 days=122.5 work/day
Step 4: Find a common denominator to add efficiencies
To add the efficiencies, we need a common denominator. The least common multiple (LCM) of 40 and 22.5 can be calculated. However, we can also convert Jack's efficiency to a fraction with a denominator of 90 for easier addition:
Efficiency of Jack=122.5=490
Efficiency of Joe=140=2.2590=9360
Step 5: Combine the efficiencies
Now we can add the efficiencies:
Combined efficiency=140+122.5=9360+16360=25360
Step 6: Calculate the time taken to complete the task together
Now that we have the combined efficiency, we can find the total time taken to complete the task together:
Total time=1 workCombined efficiency=125360=36025=14.4 days
Step 7: Convert to mixed number
To express 14.4 days as a mixed number:
14.4 days=14 days+0.4 days=14 days+25 days
Thus, the final answer is:
Joe and Jack will take 14 days and 25 days to complete the task together.
Final Answer:
14 days and 2/5 days (Option C)
Joe completes 14 of the task in 10 days. To find out how long it takes him to complete the entire task, we can set up the equation:
Jack completes 25 of the task in 9 days. To find out how long it takes him to complete the entire task, we can set up the equation:
The work rate (efficiency) is calculated as the total work divided by the total time taken. Since the total work can be considered as 1 unit of work:
Efficiency of Joe=1 work40 days=140 work/day
Efficiency of Jack=1 work22.5 days=122.5 work/day
To add the efficiencies, we need a common denominator. The least common multiple (LCM) of 40 and 22.5 can be calculated. However, we can also convert Jack's efficiency to a fraction with a denominator of 90 for easier addition:
Efficiency of Joe=140=2.2590=9360
Now we can add the efficiencies:
Now that we have the combined efficiency, we can find the total time taken to complete the task together:
To express 14.4 days as a mixed number:
14 days and 2/5 days (Option C)
Similar Questions
A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View Solution
Knowledge Check
- Question 1 - Select One
Virat can complete a task a 20 days, whereas Anu can complete the same task in 15 days. How long will it take for Virat and Anu to complete the task if they worked together
A12 12 daysB5 daysC847 daysD1712days - Question 2 - Select One
A and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
A12 daysB8 daysC14 daysD10 days - Question 3 - Select One
X can complete 57 th part of a work in 10 days and Y can complete 34 th part of the same work in 9 days. In how many days will both complete 1321 st part of the total work ?
A6B4C3D12
A and B can complete a task in 20 days, B and C can complete it in 30 days while C and A can do the same task together in 24 days. How many days will each of B and C take to complete the task individually?
View SolutionRavi can complete a task in 6 days and Mohan can complete the same task in 9 days. In how many days can Ravi and Mohan together complete the same task?
View SolutionA and B can complete a task in 50 days. B and C can complete it in 37.5 days while C and A can do the same task together in 30 days. How many days will A. B and C each take to complete the task individually?
View SolutionA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?View SolutionA and B can complete a task in 70 days. B and C can complete it in 52.5 days while C and A can do the same task together in 42 days. How many days will each of A, B and C take to complete the task individually?
View Solution