30 men working 5 hours a day can do a task in 16 days in how many days will 40 men working 6 hours a day fo the same task ?
A. 12 days
B. 10 days
C. 15 days
D. 18 days
C
B
A
D
The correct Answer is:B
To solve the problem, let's break it down step by step.
Step 1: Understand the given information
We know that:
- 30 men work 5 hours a day for 16 days to complete a task.
- We need to find out how many days (d2) it will take for 40 men working 6 hours a day to complete the same task.
Step 2: Calculate the total work done in man-hours
The total work (W) done by the first group of men can be calculated using the formula:
W=Number of Men×Hours per Day×Number of Days
For the first group:
W=30 men×5 hours/day×16 days
W=30×5×16
W=2400 man-hours
Step 3: Set up the equation for the second group
Now, we need to find out how many days (d2) it will take for 40 men working 6 hours a day to complete the same amount of work (2400 man-hours).
Using the same formula for the second group:
W=Number of Men×Hours per Day×Number of Days
For the second group:
2400=40 men×6 hours/day×d2
Step 4: Solve for d2
Now we can rearrange the equation to solve for d2:
2400=40×6×d2
2400=240×d2
d2=2400240
d2=10 days
Conclusion
Thus, it will take 40 men working 6 hours a day a total of 10 days to complete the same task.
Answer
B. 10 days
We know that:
- 30 men work 5 hours a day for 16 days to complete a task.
- We need to find out how many days (d2) it will take for 40 men working 6 hours a day to complete the same task.
The total work (W) done by the first group of men can be calculated using the formula:
W=Number of Men×Hours per Day×Number of Days
W=30 men×5 hours/day×16 days
W=30×5×16
W=2400 man-hours
Now, we need to find out how many days (d2) it will take for 40 men working 6 hours a day to complete the same amount of work (2400 man-hours).
W=Number of Men×Hours per Day×Number of Days
For the second group:
2400=40 men×6 hours/day×d2
Now we can rearrange the equation to solve for d2:
2400=40×6×d2
2400=240×d2
d2=2400240
d2=10 days
Thus, it will take 40 men working 6 hours a day a total of 10 days to complete the same task.
B. 10 days
Similar Questions
30 men working 5 h a day can do a task in 16 days. In how many days will 40 men working 6h a day do the same task?
View SolutionIf 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View Solution
Knowledge Check
- Question 1 - Select One
10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
AA)40 daysBB)60 daysCC)50 daysDD)30 days - Question 2 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15 5/21 daysB11 2/3 daysC6 9/16 daysD4 1/5 days
If 5 men working 6 hours a day can reap a field in 20 days. In how many days will 15 men reap the field, working 8 hours a day ?
View SolutionTwelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
View SolutionTwelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?
View SolutionSixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
View SolutionSixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
View Solution