A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in
40 days
24 days
120 days
13 days
The correct Answer is:A
To solve the problem step by step, we can follow these calculations:
Step 1: Determine the total work
Given that:
- A and B can finish the work in 15 days
- B and C can finish the work in 20 days
- C and A can finish the work in 30 days
To find the total work, we can take the least common multiple (LCM) of the days taken by each pair:
- LCM of 15, 20, and 30 is 60.
So, we can consider the total work as 60 units.
Step 2: Calculate the work done by each pair in one day
1. A and B's work in one day:
Work done by A and B in one day=6015=4 units
2. B and C's work in one day:
Work done by B and C in one day=6020=3 units
3. C and A's work in one day:
Work done by C and A in one day=6030=2 units
Step 3: Set up equations for the efficiencies
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c
From the work done in one day, we can set up the following equations:
1. a+b=4 (from A and B)
2. b+c=3 (from B and C)
3. c+a=2 (from C and A)
Step 4: Solve the equations
We can add all three equations:
(a+b)+(b+c)+(c+a)=4+3+2
This simplifies to:
2a+2b+2c=9
Dividing by 2:
a+b+c=4.5
Now, we can find the individual efficiencies:
1. From a+b=4:
c=4.5−4=0.5
2. From b+c=3:
b+0.5=3⟹b=3−0.5=2.5
3. From c+a=2:
0.5+a=2⟹a=2−0.5=1.5
Step 5: Calculate the time taken by A alone to finish the work
Now, we know the efficiency of A:
Efficiency of A=a=1.5 units/day
To find out how many days A will take to complete the total work of 60 units:
Time taken by A=Total WorkEfficiency of A=601.5=40 days
Final Answer
A alone can finish the work in 40 days.
Given that:
- A and B can finish the work in 15 days
- B and C can finish the work in 20 days
- C and A can finish the work in 30 days
- LCM of 15, 20, and 30 is 60.
1. A and B's work in one day:
Work done by A and B in one day=6015=4 units
Work done by B and C in one day=6020=3 units
Work done by C and A in one day=6030=2 units
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c
1. a+b=4 (from A and B)
2. b+c=3 (from B and C)
3. c+a=2 (from C and A)
We can add all three equations:
(a+b)+(b+c)+(c+a)=4+3+2
This simplifies to:
2a+2b+2c=9
Dividing by 2:
a+b+c=4.5
1. From a+b=4:
c=4.5−4=0.5
b+0.5=3⟹b=3−0.5=2.5
0.5+a=2⟹a=2−0.5=1.5
Now, we know the efficiency of A:
Efficiency of A=a=1.5 units/day
Time taken by A=Total WorkEfficiency of A=601.5=40 days
A alone can finish the work in 40 days.
Topper's Solved these Questions
- BOOK - ARIHANT PUBLICATION PUNJABCHAPTER - SOLVED PAPER 2018EXERCISE - SECTION D MATHEMATICS30videos
SOLVED PAPER 2018
- BOOK - ARIHANT PUBLICATION PUNJABCHAPTER - SOLVED PAPER 2016EXERCISE - Section D (Mathematics)30videos
SOLVED PAPER 2016
- BOOK - ARIHANT PUBLICATION PUNJABCHAPTER - SQUARE-SQUARE ROOT AND CUBE-CUBE ROOTEXERCISE - Chapter Exercise70videos
SQUARE-SQUARE ROOT AND CUBE-CUBE ROOT
Similar Questions
A and B can finish a work in 12 days, B and C in 15 days and A and C in 20 days. In how many days would A along finish the work?
(A) 20
(B) 30
(C) 40
(D) 60View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
If A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in
A427 daysB30 daysC847 daysD760 days - Question 2 - Select One
A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
A60 daysB120 daysC80 daysD30 days - Question 3 - Select One
A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
A1523B24 daysC30 daysD40 days
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How much time will A alone take to finish the job ?
View SolutionX and Y together can finish a piece of work in 15 days, while Y alone can finish it in 40 days. X alone can finish the work in:
View SolutionA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
View SolutionA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
View Solution