Doubtnut Promotions Sticky

A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in

A

40 days

B

24 days

C

120 days

D

13 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these calculations:

Step 1: Determine the total work
Given that:
- A and B can finish the work in 15 days
- B and C can finish the work in 20 days
- C and A can finish the work in 30 days

To find the total work, we can take the least common multiple (LCM) of the days taken by each pair:
- LCM of 15, 20, and 30 is 60.

So, we can consider the total work as 60 units.

Step 2: Calculate the work done by each pair in one day
1. A and B's work in one day:
Work done by A and B in one day=6015=4 units

2. B and C's work in one day:
Work done by B and C in one day=6020=3 units

3. C and A's work in one day:
Work done by C and A in one day=6030=2 units

Step 3: Set up equations for the efficiencies
Let:
- Efficiency of A = a
- Efficiency of B = b
- Efficiency of C = c

From the work done in one day, we can set up the following equations:
1. a+b=4 (from A and B)
2. b+c=3 (from B and C)
3. c+a=2 (from C and A)

Step 4: Solve the equations
We can add all three equations:
(a+b)+(b+c)+(c+a)=4+3+2
This simplifies to:
2a+2b+2c=9
Dividing by 2:
a+b+c=4.5

Now, we can find the individual efficiencies:
1. From a+b=4:
c=4.54=0.5

2. From b+c=3:
b+0.5=3b=30.5=2.5

3. From c+a=2:
0.5+a=2a=20.5=1.5

Step 5: Calculate the time taken by A alone to finish the work
Now, we know the efficiency of A:
Efficiency of A=a=1.5 units/day

To find out how many days A will take to complete the total work of 60 units:
Time taken by A=Total WorkEfficiency of A=601.5=40 days

Final Answer
A alone can finish the work in 40 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If A and B together can finish a piece of work in 20 days, B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in

    A427 days
    B30 days
    C847 days
    D760 days
  • Question 2 - Select One

    A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

    A60 days
    B120 days
    C80 days
    D30 days
  • Question 3 - Select One

    A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?

    A1523
    B24 days
    C30 days
    D40 days