10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
A)40 days
B)60 days
C)50 days
D)30 days
The correct Answer is:C
To solve the problem, we need to determine how many days it will take for 12 men working 4 hours a day to complete the same work that 10 men can complete in 30 days working 8 hours a day.
1. Calculate the total work done in man-hours by the first group:
- Number of men = 10
- Hours per day = 8
- Number of days = 30
Total work (in man-hours) = Number of men × Hours per day × Number of days
Total work=10men×8hours/day×30days=2400man-hours
2. Set up the equation for the second group:
- Number of men = 12
- Hours per day = 4
- Number of days = d2 (unknown)
Total work done by the second group can be expressed as:
Total work=12men×4hours/day×d2days
3. Equate the total work from both groups:
Since both groups are doing the same work, we can set the equations equal to each other:
2400man-hours=12men×4hours/day×d2
4. Simplify the equation:
2400=48d2
5. Solve for d2:
d2=240048=50
Thus, it will take 12 men working 4 hours a day a total of 50 days to complete the same work.
- Number of men = 10
- Hours per day = 8
- Number of days = 30
Total work=10men×8hours/day×30days=2400man-hours
- Number of men = 12
- Hours per day = 4
- Number of days = d2 (unknown)
Total work=12men×4hours/day×d2days
Since both groups are doing the same work, we can set the equations equal to each other:
2400man-hours=12men×4hours/day×d2
2400=48d2
d2=240048=50
Similar Questions
Knowledge Check
- Question 1 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days - Question 2 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15 5/21 daysB11 2/3 daysC6 9/16 daysD4 1/5 days - Question 3 - Select One
30 men working 5 hours a day can do a task in 16 days in how many days will 40 men working 6 hours a day fo the same task ?
A. 12 days
B. 10 days
C. 15 days
D. 18 daysACBBCADD
Twelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?
View SolutionSixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
View SolutionSixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
View SolutionIf 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View SolutionIf 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212
View Solution