The work will have be completed by the time we get there.
The work will have been completed by the time we get.
The work will have been completed by the time we get there.
The work will have completed the time we get there.
The work will have been completed by the time we have got there.
The correct Answer is:B
Similar Practice Problems
- Question 1 - Select One
Bunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :
A16 daysB24 daysC12 daysD1313 days - Question 1 - Select One
Bunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :
A8 daysB3835 daysC152D1313 - Question 1 - Select One
Two workers A and B working together completed a job in 5
days. If A worked twice as efficiently as he actually did and
B worked 1/3 as efficiently as he actually did, the work would
have completed in 3 days. Fine the time for A to complete
the job alone.A614 daysB534 daysC5 daysD3 days - Question 1 - Select One
By that time tomorrow, they would have completed the work allotted to them.
ABy that time tomorrow, the work allotted to them would be completed by them.BBy that time tomorrow. the work allotted to them would complete by them.CBy that time tomorrow, the work allotted to them would be complete by them.DBy that time tomorrow, the work allotted to them would have been completed by them. - Question 1 - Select One
Janardan completes 23 of his work in 10 days. Time he will take to complete 35 of the same work, is
A8 daysB6 daysC9 daysD4 days - Question 1 - Select One
I said, "I have completed my work."
AI said that I have completed my work.BI said that I have complete your work.CI said that I had completed my work.DI told that I have completed my work.
Similar Questions
Tushar takes 6 hours to complete a piece of work, while Amar completes the same work in 10 hours. If both of them work together, then what is the time required to complete the work?
View SolutionIf three times the larger of the two numbers is divided by the smaller, we get the quotient 6 and remainder 6. If five times the smaller is divided by the larger, we get quotient 2 and remainder 3. Find the numbers.
View SolutionIf three times the larger of the two numbers is divided by the smaller, we get the quotient 6 and remainder 6. If five times the smaller is divided by the larger, we get quotient 2 and remainder 3. Find the numbers.
View SolutionX works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.
View Solution