If 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
A
15
B
30
C
20
D
35
Text Solution
The correct Answer is:C
|
Updated on:21/07/2023
Similar Questions
Knowledge Check
- Question 1 - Select One
If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
A4B5C14D10 - Question 2 - Select One
If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
A40B20C14D10 - Question 3 - Select One
If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
A38B28C19D17
If 8 men can do a piece of work in 15 days, how many men are required to do the same piece of work in 10 days ?
View SolutionIf 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View SolutionIf 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View SolutionIf x men can do a piece of work In x days, then the number of days in which y men can do the same work is
View SolutionTwelve persons can do a piece of work in 20 days. How many persons are required to do the same in 24 days?
View Solution