A person has undertaken a construction job. The probablities are 0.65 that will be strike, 0.80 that the construction job will becompleted on time if there is no strike, and 0.32 that the construction job will be completed on time if there is a strike. Then the probability that the construction job will be completed on time is
0.788
0.488
1.488
1.634
The correct Answer is:B
To find the probability that the construction job will be completed on time, we can use the law of total probability. We will consider two scenarios: when there is a strike and when there is no strike.
1. Identify Given Probabilities:
- Probability of strike (P(S)) = 0.65
- Probability of no strike (P(S')) = 1 - P(S) = 1 - 0.65 = 0.35
- Probability of completing the job on time if there is a strike (P(C|S)) = 0.32
- Probability of completing the job on time if there is no strike (P(C|S')) = 0.80
2. Apply the Law of Total Probability:
The total probability of completing the job on time (P(C)) can be calculated as:
P(C)=P(S)⋅P(C|S)+P(S′)⋅P(C|S′)
3. Substitute the Values:
P(C)=(0.65⋅0.32)+(0.35⋅0.80)
4. Calculate Each Term:
- Calculate 0.65⋅0.32:
0.65⋅0.32=0.208
- Calculate 0.35⋅0.80:
0.35⋅0.80=0.28
5. Add the Results:
P(C)=0.208+0.28=0.488
6. Final Result:
The probability that the construction job will be completed on time is:
P(C)=0.488
- Probability of strike (P(S)) = 0.65
- Probability of no strike (P(S')) = 1 - P(S) = 1 - 0.65 = 0.35
- Probability of completing the job on time if there is a strike (P(C|S)) = 0.32
- Probability of completing the job on time if there is no strike (P(C|S')) = 0.80
The total probability of completing the job on time (P(C)) can be calculated as:
P(C)=P(S)⋅P(C|S)+P(S′)⋅P(C|S′)
P(C)=(0.65⋅0.32)+(0.35⋅0.80)
- Calculate 0.65⋅0.32:
0.65⋅0.32=0.208
- Calculate 0.35⋅0.80:
0.35⋅0.80=0.28
P(C)=0.208+0.28=0.488
The probability that the construction job will be completed on time is:
P(C)=0.488
Similar Questions
A person has undertaken a construction job. The probabilities are 0.65 that there will be strike. 0.80 that the construction job will be completed on time if there is no strike, and 0.32 that the construction job will be completed on time if ther
View SolutionA person has undertaken a construction job. The probabilities are 0.80 that there will be a strike, 0.70 that the construction job will be completed on time if there is no strike, and 0.4 that the construction job will be completed on time if there is a strike. Determine the probability that the construction job will be completed on time.
View Solution
Knowledge Check
If the probability that Mike will miss at least one of ten jobs assigned to him is 0.55, then what is the probability that he will do all ten jobs?
A0.1B0.45C0.55D0.85
A man takes the contract of construction work. The probability is 0.30, if there will be no strike. The probability that the construct work will be completed on time are 0.8 and 0.3 in cases of no strike and in case strike respectively. Find the probability that the construction work will be completed in time.
View SolutionTwo dice are thrown at the same time. Find the probability that the sum of the two numbers appearing on the top of the disc is:
0
View SolutionThe coefficients a,b and c of the quadratic equation, ax2+bx+c = 0 are obtained by throwing a dice three times. The probability that this equation has equal roots is:
View SolutionThe least number of times a fair coin must be tossed so that the probability of getting atleast one head is atleast 0.8 is
View SolutionA matrix is chosen at random from the set of all 2×2 matrices with elements 0 and 1 only. The probability that positive, is
View SolutionWhat is the time taken to complete 75 percent of the reaction if the rate of the first-order reaction is 0.023 min-1?
View SolutionThe probability that a man will hit a target in shooting practise is 0.3. If he shoots 10 times, the probability that he hits the target , is
View Solution