Doubtnut Promotions Sticky

If 10 men and 15 women complete a piece of work in 8 days while 12 men and 8 women can complete the same piece of work in 10 days. If A boy who is 50% less efficient than the man, can do the same work in 50 days.
Quantity I: Time taken by 2 men, 4 women and 18 boys to complete the work.
Quantity II: Time taken by 9 men, 3 women and 6 boys to complete the same work.

A

Quantity I > Quantity II

B

Quantity I < Quantity II

C

Quantity I ≥Quantity II

D

Quantity I = Quantity II or No relation

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the efficiency of men, women, and boys based on the information provided.

Step 1: Determine the work done by men and women

We know:
- 10 men and 15 women complete the work in 8 days.
- 12 men and 8 women complete the work in 10 days.

Let the work done by 1 man in 1 day be m and the work done by 1 woman in 1 day be w.

From the first scenario:
10m+15w=18(since they complete the work in 8 days)
This can be rewritten as:
80m+120w=1(multiplying through by 8)

From the second scenario:
12m+8w=110(since they complete the work in 10 days)
This can be rewritten as:
120m+80w=1(multiplying through by 10)

Step 2: Set up the equations

Now we have two equations:
1. 80m+120w=1 (Equation 1)
2. 120m+80w=1 (Equation 2)

Step 3: Solve the equations

We can solve these equations simultaneously. Let's multiply Equation 1 by 3 and Equation 2 by 2 to eliminate w:

From Equation 1:
240m+360w=3(multiplying by 3)

From Equation 2:
240m+160w=2(multiplying by 2)

Now subtract the second from the first:
(240m+360w)−(240m+160w)=3−2
200w=1⟹w=1200

Substituting w back into Equation 1 to find m:
80m+120(1200)=1
80m+120200=1
80m+35=1
80m=1−35=25
m=2400=1200

Step 4: Determine the efficiency of boys

A boy is 50% less efficient than a man, so:
b=m2=1/2002=1400

Step 5: Calculate Quantity I

For Quantity I, we need to find the time taken by 2 men, 4 women, and 18 boys:
Total work done per day=2m+4w+18b
Substituting the values:
=2(1200)+4(1200)+18(1400)
=2200+4200+18400
=6200+18400
Converting 18400 to a common denominator:
18400=9200
So,
=6200+9200=15200=340

The time taken to complete the work:
Time=1Total work done per day=1340=403 days

Step 6: Calculate Quantity II

For Quantity II, we need to find the time taken by 9 men, 3 women, and 6 boys:
Total work done per day=9m+3w+6b
Substituting the values:
=9(1200)+3(1200)+6(1400)
=9200+3200+6400
Converting 6400 to a common denominator:
6400=3200
So,
=9200+3200+3200=15200=340

The time taken to complete the work:
Time=1Total work done per day=1340=403 days

Conclusion

Both quantities are equal:
Quantity I=Quantity II=403 days

Thus, the answer is:
Quantity I = Quantity II

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?

    A6days
    B5days
    C4days
    D7days
  • Question 2 - Select One

    If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

    A4 days
    B5 days
    C3 days
    D2 days
  • Question 3 - Select One

    6 men or 10 boys can complete a piece of work in 15 days. If 7 men and x boys complete the same piece of work in 9 days, then x is equal to

    A4
    B5
    C6
    D7