If 10 men and 15 women complete a piece of work in 8 days while 12 men and 8 women can complete the same piece of work in 10 days. If A boy who is 50% less efficient than the man, can do the same work in 50 days.
Quantity I: Time taken by 2 men, 4 women and 18 boys to complete the work.
Quantity II: Time taken by 9 men, 3 women and 6 boys to complete the same work.
Quantity I > Quantity II
Quantity I < Quantity II
Quantity I ≥Quantity II
Quantity I = Quantity II or No relation
The correct Answer is:D
To solve the problem step by step, we will first determine the efficiency of men, women, and boys based on the information provided.
Step 1: Determine the work done by men and women
We know:
- 10 men and 15 women complete the work in 8 days.
- 12 men and 8 women complete the work in 10 days.
Let the work done by 1 man in 1 day be m and the work done by 1 woman in 1 day be w.
From the first scenario:
10m+15w=18(since they complete the work in 8 days)
This can be rewritten as:
80m+120w=1(multiplying through by 8)
From the second scenario:
12m+8w=110(since they complete the work in 10 days)
This can be rewritten as:
120m+80w=1(multiplying through by 10)
Step 2: Set up the equations
Now we have two equations:
1. 80m+120w=1 (Equation 1)
2. 120m+80w=1 (Equation 2)
Step 3: Solve the equations
We can solve these equations simultaneously. Let's multiply Equation 1 by 3 and Equation 2 by 2 to eliminate w:
From Equation 1:
240m+360w=3(multiplying by 3)
From Equation 2:
240m+160w=2(multiplying by 2)
Now subtract the second from the first:
(240m+360w)−(240m+160w)=3−2
200w=1⟹w=1200
Substituting w back into Equation 1 to find m:
80m+120(1200)=1
80m+120200=1
80m+35=1
80m=1−35=25
m=2400=1200
Step 4: Determine the efficiency of boys
A boy is 50% less efficient than a man, so:
b=m2=1/2002=1400
Step 5: Calculate Quantity I
For Quantity I, we need to find the time taken by 2 men, 4 women, and 18 boys:
Total work done per day=2m+4w+18b
Substituting the values:
=2(1200)+4(1200)+18(1400)
=2200+4200+18400
=6200+18400
Converting 18400 to a common denominator:
18400=9200
So,
=6200+9200=15200=340
The time taken to complete the work:
Time=1Total work done per day=1340=403 days
Step 6: Calculate Quantity II
For Quantity II, we need to find the time taken by 9 men, 3 women, and 6 boys:
Total work done per day=9m+3w+6b
Substituting the values:
=9(1200)+3(1200)+6(1400)
=9200+3200+6400
Converting 6400 to a common denominator:
6400=3200
So,
=9200+3200+3200=15200=340
The time taken to complete the work:
Time=1Total work done per day=1340=403 days
Conclusion
Both quantities are equal:
Quantity I=Quantity II=403 days
Thus, the answer is:
Quantity I = Quantity II
- 10 men and 15 women complete the work in 8 days.
- 12 men and 8 women complete the work in 10 days.
10m+15w=18(since they complete the work in 8 days)
This can be rewritten as:
80m+120w=1(multiplying through by 8)
12m+8w=110(since they complete the work in 10 days)
This can be rewritten as:
120m+80w=1(multiplying through by 10)
1. 80m+120w=1 (Equation 1)
2. 120m+80w=1 (Equation 2)
240m+360w=3(multiplying by 3)
240m+160w=2(multiplying by 2)
(240m+360w)−(240m+160w)=3−2
200w=1⟹w=1200
80m+120(1200)=1
80m+120200=1
80m+35=1
80m=1−35=25
m=2400=1200
b=m2=1/2002=1400
Total work done per day=2m+4w+18b
Substituting the values:
=2(1200)+4(1200)+18(1400)
=2200+4200+18400
=6200+18400
Converting 18400 to a common denominator:
18400=9200
So,
=6200+9200=15200=340
Time=1Total work done per day=1340=403 days
Total work done per day=9m+3w+6b
Substituting the values:
=9(1200)+3(1200)+6(1400)
=9200+3200+6400
Converting 6400 to a common denominator:
6400=3200
So,
=9200+3200+3200=15200=340
Time=1Total work done per day=1340=403 days
Quantity I=Quantity II=403 days
Quantity I = Quantity II
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - INEQUALITYEXERCISE - Previous Year Questions75videos
INEQUALITY
- BOOK - ADDA247CHAPTER - INEQUALITYEXERCISE - Prelims Questions (Level - 2)55videos
INEQUALITY
- BOOK - ADDA247CHAPTER - DATA SUFFICIENCY EXERCISE - PREVIOUS YEAR QUESTIONS25videos
DATA SUFFICIENCY
- BOOK - ADDA247CHAPTER - MENSURATION EXERCISE - PREVIOUS YEAR QUESTION31videos
MENSURATION
Similar Questions
8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.
View Solution2 men and 3 women can do a piece of work in 10 days, while 3 men nd 2 women can do the same work in 8 days. Then, 2 men and 1 woman can do the same work in
View Solution
Knowledge Check
- Question 1 - Select One
21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
A6daysB5daysC4daysD7days - Question 2 - Select One
If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
A4 daysB5 daysC3 daysD2 days - Question 3 - Select One
6 men or 10 boys can complete a piece of work in 15 days. If 7 men and x boys complete the same piece of work in 9 days, then x is equal to
A4B5C6D7
4 men and 6 women can complete a work in 8 days, While 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it.
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View SolutionIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
View SolutionIf 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be
View Solution4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
View Solution