Following are the questions based on two statements and answer the following based on the given statements.
C alone can complete the work in 15 days. In what time C and A together can complete the whole work.
Statement I. A is 25% more efficient than B and B alone can complete the work in 20 days
Statement II. Difference between the time taken by A alone and B alone to complete the work is 22 days , and time taken by C alone to finish the work is 10% more than the time taken by A and B together to complete the work.
Statement I alone is sufficient to answer the question while statement II alone is not sufficient to answer the question
tatement II alone is sufficient to answer the question while statement I alone is not sufficient to answer the question
Both statements I and II together are required to tedes answer the question.
Either the statement I alone or Statement II alone Vis sufficient to answer the question
The correct Answer is:D
To solve the problem, we need to determine how long A and C together will take to complete the work, given the information from the two statements.
1. Understanding the Work Rates:
- C can complete the work alone in 15 days. Therefore, C's work rate is:
Work rate of C=115 (work/day)
2. Analyzing Statement I:
- A is 25% more efficient than B, and B can complete the work in 20 days.
- B's work rate is:
Work rate of B=120 (work/day)
- Since A is 25% more efficient than B, we can calculate A's work rate as follows:
Efficiency of A=Efficiency of B×1.25
Work rate of A=120×1.25=1.2520=116 (work/day)
3. Calculating Combined Work Rate of A and C:
- Now, we can find the combined work rate of A and C:
Combined work rate of A and C=Work rate of A+Work rate of C
=116+115
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 16 and 15 is 240.
116=15240,115=16240
Combined work rate=15240+16240=31240 (work/day)
4. Calculating Time Taken by A and C Together:
- The time taken by A and C together to complete the work is the reciprocal of their combined work rate:
Time=1Combined work rate=24031 days
5. Conclusion:
- A and C together can complete the work in 24031 days.
- C can complete the work alone in 15 days. Therefore, C's work rate is:
Work rate of C=115 (work/day)
- A is 25% more efficient than B, and B can complete the work in 20 days.
- B's work rate is:
Work rate of B=120 (work/day)
- Since A is 25% more efficient than B, we can calculate A's work rate as follows:
Efficiency of A=Efficiency of B×1.25
Work rate of A=120×1.25=1.2520=116 (work/day)
- Now, we can find the combined work rate of A and C:
Combined work rate of A and C=Work rate of A+Work rate of C
=116+115
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 16 and 15 is 240.
116=15240,115=16240
Combined work rate=15240+16240=31240 (work/day)
- The time taken by A and C together to complete the work is the reciprocal of their combined work rate:
Time=1Combined work rate=24031 days
- A and C together can complete the work in 24031 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days - Question 2 - Select One
If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?
A24 daysB15 daysC8 daysD18 days - Question 3 - Select One
NiNAl can alone complete a work in 20 days. Suresh is 25% more efficient than her. He can complete the work in __ days.
A14B16C18D20
A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View SolutionIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
View SolutionA alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View Solution