The time taken by A alone to finish a piece of work is 60% more than that taken by A and B together to finish the same piece of work. C is twice as efficient as B. If B and C together can complete the same piece of work in 13'13 days, in how many days can A alone finish the same piece of work?
32
24
16
28
The correct Answer is:B
To solve the problem, we will follow these steps:
Step 1: Define Variables
Let the time taken by A and B together to complete the work be X days.
Step 2: Express A's Time
Since A takes 60% more time than A and B together, the time taken by A alone to complete the work is:
A′stime=X+0.6X=1.6X
Step 3: Determine B and C's Efficiency
We know that B and C together can complete the work in 1313 days, which is equivalent to 403 days. Therefore, their combined work rate is:
Work rate of B and C=1403=340 work per day
Step 4: Set Up B and C's Individual Rates
Let the work rate of B be b and that of C be c. Since C is twice as efficient as B, we have:
c=2b
Thus, the combined work rate of B and C can be expressed as:
b+c=b+2b=3b
Setting this equal to the combined work rate we found:
3b=340
From this, we can solve for b:
b=140 work per day
Step 5: Calculate C's Rate
Using b to find c:
c=2b=2×140=120 work per day
Step 6: Find A and B's Combined Rate
Now, we can find the combined work rate of A and B. Since A's work rate is unknown, we denote it as a. The combined work rate of A and B is:
a+b=a+140
Step 7: Relate A's Rate to X
Since A and B together complete the work in X days, their combined work rate is:
1X=a+140
From this, we can express a:
a=1X−140
Step 8: Substitute A's Time
Now substitute a into the equation for A's time:
1.6X=1a=1(1X−140)
Taking the reciprocal:
1.6X=X⋅4040−X
Step 9: Solve for X
Cross-multiplying gives:
1.6X(40−X)=40X
Expanding:
64X−1.6X2=40X
Rearranging:
1.6X2−24X=0
Factoring out X:
X(1.6X−24)=0
Thus, X=0 or X=15.
Step 10: Calculate A's Time
Now substituting X=15 back into the equation for A's time:
A′stime=1.6X=1.6×15=24 days
Final Answer
A can finish the work alone in 24 days.
---
Let the time taken by A and B together to complete the work be X days.
Since A takes 60% more time than A and B together, the time taken by A alone to complete the work is:
A′stime=X+0.6X=1.6X
We know that B and C together can complete the work in 1313 days, which is equivalent to 403 days. Therefore, their combined work rate is:
Work rate of B and C=1403=340 work per day
Let the work rate of B be b and that of C be c. Since C is twice as efficient as B, we have:
c=2b
Thus, the combined work rate of B and C can be expressed as:
b+c=b+2b=3b
Setting this equal to the combined work rate we found:
3b=340
From this, we can solve for b:
b=140 work per day
Using b to find c:
c=2b=2×140=120 work per day
Now, we can find the combined work rate of A and B. Since A's work rate is unknown, we denote it as a. The combined work rate of A and B is:
a+b=a+140
Since A and B together complete the work in X days, their combined work rate is:
1X=a+140
From this, we can express a:
a=1X−140
Now substitute a into the equation for A's time:
1.6X=1a=1(1X−140)
Taking the reciprocal:
1.6X=X⋅4040−X
Cross-multiplying gives:
1.6X(40−X)=40X
Expanding:
64X−1.6X2=40X
Rearranging:
1.6X2−24X=0
Factoring out X:
X(1.6X−24)=0
Thus, X=0 or X=15.
Now substituting X=15 back into the equation for A's time:
A′stime=1.6X=1.6×15=24 days
A can finish the work alone in 24 days.
Similar Questions
Knowledge Check
A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
A18B20C21D24A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A18B20C21D24If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
A60 daysB45 daysC40 daysD30 days
A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View SolutionA is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
View SolutionA alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
View SolutionA is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
View Solution