Doubtnut Promotions Sticky

Vijay and Sahil together complete a piece of work in 40 days, Sahil and Ranjit can complete the same work in 48 days and Ranjit and Vijay can complete the same work in 60 days. In how many days can all the three complete the same work while working together?

A

16

B

24

C

32

D

38

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to find out how many days Vijay, Sahil, and Ranjit can complete the work together. We will use the concept of work rates.

1. Define Work Rates:
Let the work rates of Vijay, Sahil, and Ranjit be V, S, and R respectively. The work done is inversely proportional to the time taken.

2. Set Up Equations:
From the information given:
- Vijay and Sahil together complete the work in 40 days:
V+S=140(Equation 1)
- Sahil and Ranjit together complete the work in 48 days:
S+R=148(Equation 2)
- Ranjit and Vijay together complete the work in 60 days:
R+V=160(Equation 3)

3. Add the Equations:
Now, we will add all three equations:
(V+S)+(S+R)+(R+V)=140+148+160
This simplifies to:
2V+2S+2R=140+148+160
Dividing the entire equation by 2:
V+S+R=12(140+148+160)

4. Calculate the Right Side:
We need to find a common denominator for 40,48, and 60. The LCM of these numbers is 240.
140=6240,148=5240,160=4240
Adding these fractions:
6240+5240+4240=15240=116

5. Substituting Back:
Now substituting back into our equation:
V+S+R=12(116)=132

6. Conclusion:
Therefore, the time taken by all three working together to complete the work is:
Time=1V+S+R=1132=32 days

Final Answer: Vijay, Sahil, and Ranjit together can complete the work in 32 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

    A12013 days
    B48013 days
    C24013 days
    D96013 days
  • Question 2 - Select One

    A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

    A6 days
    B4 days
    C10 days
    D8 days
  • Question 3 - Select One

    A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

    A4813 days
    B3513 days
    C267 days
    D247 days