Vijay and Sahil together complete a piece of work in 40 days, Sahil and Ranjit can complete the same work in 48 days and Ranjit and Vijay can complete the same work in 60 days. In how many days can all the three complete the same work while working together?
16
24
32
38
The correct Answer is:C
To solve the problem, we need to find out how many days Vijay, Sahil, and Ranjit can complete the work together. We will use the concept of work rates.
1. Define Work Rates:
Let the work rates of Vijay, Sahil, and Ranjit be V, S, and R respectively. The work done is inversely proportional to the time taken.
2. Set Up Equations:
From the information given:
- Vijay and Sahil together complete the work in 40 days:
V+S=140(Equation 1)
- Sahil and Ranjit together complete the work in 48 days:
S+R=148(Equation 2)
- Ranjit and Vijay together complete the work in 60 days:
R+V=160(Equation 3)
3. Add the Equations:
Now, we will add all three equations:
(V+S)+(S+R)+(R+V)=140+148+160
This simplifies to:
2V+2S+2R=140+148+160
Dividing the entire equation by 2:
V+S+R=12(140+148+160)
4. Calculate the Right Side:
We need to find a common denominator for 40,48, and 60. The LCM of these numbers is 240.
140=6240,148=5240,160=4240
Adding these fractions:
6240+5240+4240=15240=116
5. Substituting Back:
Now substituting back into our equation:
V+S+R=12(116)=132
6. Conclusion:
Therefore, the time taken by all three working together to complete the work is:
Time=1V+S+R=1132=32 days
Final Answer: Vijay, Sahil, and Ranjit together can complete the work in 32 days.
Let the work rates of Vijay, Sahil, and Ranjit be V, S, and R respectively. The work done is inversely proportional to the time taken.
From the information given:
- Vijay and Sahil together complete the work in 40 days:
V+S=140(Equation 1)
- Sahil and Ranjit together complete the work in 48 days:
S+R=148(Equation 2)
- Ranjit and Vijay together complete the work in 60 days:
R+V=160(Equation 3)
Now, we will add all three equations:
(V+S)+(S+R)+(R+V)=140+148+160
This simplifies to:
2V+2S+2R=140+148+160
Dividing the entire equation by 2:
V+S+R=12(140+148+160)
We need to find a common denominator for 40,48, and 60. The LCM of these numbers is 240.
140=6240,148=5240,160=4240
Adding these fractions:
6240+5240+4240=15240=116
Now substituting back into our equation:
V+S+R=12(116)=132
Therefore, the time taken by all three working together to complete the work is:
Time=1V+S+R=1132=32 days
Similar Questions
Knowledge Check
- Question 1 - Select One
A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?
A12013 daysB48013 daysC24013 daysD96013 days - Question 2 - Select One
A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
A6 daysB4 daysC10 daysD8 days - Question 3 - Select One
A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
A4813 daysB3513 daysC267 daysD247 days
Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View SolutionA and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View Solution