A and B can do a piece of work in 12 days. A is one and a half times more efficient than B. In how many days does A complete the work independently?

A

25

B

15

C

30

D

20

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first define the efficiencies of A and B, then calculate the total work done, and finally determine how long A would take to complete the work independently.

Step 1: Define the efficiencies of A and B
Let the efficiency of B be x. Since A is one and a half times more efficient than B, the efficiency of A will be:
Efficiency of A=1.5x

Step 2: Calculate the combined efficiency of A and B
The combined efficiency of A and B is the sum of their individual efficiencies:
Combined efficiency=Efficiency of A+Efficiency of B=1.5x+x=2.5x

Step 3: Determine the total work done
According to the problem, A and B can complete the work together in 12 days. Therefore, the total work can be calculated as:
Total Work=Combined Efficiency×Time=2.5x×12
Total Work=30x

Step 4: Calculate the time taken by A to complete the work independently
Now, we need to find out how many days A would take to complete the total work of 30x alone. The work done by A in one day is 1.5x. Therefore, the number of days A takes to complete the work is given by:
Days taken by A=Total WorkEfficiency of A=30x1.5x
Days taken by A=301.5=20

Conclusion
A can complete the work independently in 20 days.

---

Updated on:8/8/2024
|