A and B can do a piece of work in 12 days. A is one and a half times more efficient than B. In how many days does A complete the work independently?
25
15
30
20
The correct Answer is:D
To solve the problem step by step, we will first define the efficiencies of A and B, then calculate the total work done, and finally determine how long A would take to complete the work independently.
Step 1: Define the efficiencies of A and B
Let the efficiency of B be x. Since A is one and a half times more efficient than B, the efficiency of A will be:
Efficiency of A=1.5x
Step 2: Calculate the combined efficiency of A and B
The combined efficiency of A and B is the sum of their individual efficiencies:
Combined efficiency=Efficiency of A+Efficiency of B=1.5x+x=2.5x
Step 3: Determine the total work done
According to the problem, A and B can complete the work together in 12 days. Therefore, the total work can be calculated as:
Total Work=Combined Efficiency×Time=2.5x×12
Total Work=30x
Step 4: Calculate the time taken by A to complete the work independently
Now, we need to find out how many days A would take to complete the total work of 30x alone. The work done by A in one day is 1.5x. Therefore, the number of days A takes to complete the work is given by:
Days taken by A=Total WorkEfficiency of A=30x1.5x
Days taken by A=301.5=20
Conclusion
A can complete the work independently in 20 days.
---
Let the efficiency of B be x. Since A is one and a half times more efficient than B, the efficiency of A will be:
Efficiency of A=1.5x
The combined efficiency of A and B is the sum of their individual efficiencies:
Combined efficiency=Efficiency of A+Efficiency of B=1.5x+x=2.5x
According to the problem, A and B can complete the work together in 12 days. Therefore, the total work can be calculated as:
Total Work=Combined Efficiency×Time=2.5x×12
Total Work=30x
Now, we need to find out how many days A would take to complete the total work of 30x alone. The work done by A in one day is 1.5x. Therefore, the number of days A takes to complete the work is given by:
Days taken by A=Total WorkEfficiency of A=30x1.5x
Days taken by A=301.5=20
A can complete the work independently in 20 days.
Similar Questions
Knowledge Check
A and B can do a job together in 12days . A is 2 times as efficient as B . In how many days can B alones complete the work ?
A36B12C18D9A can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
A12B16C18D15A can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?
A214B257C245D203
A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in
View SolutionA can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA can do a piece of work in 40 days. B does the same work with 60% more efficiency. How many days will B take to complete the work alone?
View SolutionA alone can do a work in 15 days. A is 20% less efficient than B. In how many days can B alone do the work?
View SolutionA can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
View Solution