45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
6
4
3
5
The correct Answer is:A
Step by step video, text & image solution for 45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Topper's Solved these Questions
- BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - SOF INTERNATIONAL MATHEMATICS OLYMPIAD QUESTION PAPER 2020EXERCISE - ACHIEVERS SECTION4videos
SOF INTERNATIONAL MATHEMATICS OLYMPIAD QUESTION PAPER 2020
- BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - SOF INTERNATIONAL MATHEMATICS OLYMPIAD QUESTION PAPER 2020EXERCISE - LOGICAL REASONING1videos
SOF INTERNATIONAL MATHEMATICS OLYMPIAD QUESTION PAPER 2020
- BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - SOF INTERNATIONAL MATHEMATICS OLYMPIAD QUESTION PAPER 2020EXERCISE - LOGICAL REASONING1videos
SOF INTERNATIONAL MATHEMATICS OLYMPIAD QUESTION PAPER 2020
- BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - SAMPLE PAPER 4 (CLASS 10)EXERCISE - Section E - Logical Reasoning1videos
SAMPLE PAPER 4 (CLASS 10)
- BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - SOME APPLICATIONS OF TRIGONOMETRY EXERCISE - ACHIEVERS SECTION (HOTS)5videos
SOME APPLICATIONS OF TRIGONOMETRY
Similar Questions
14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View SolutionTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View Solution
Knowledge Check
- Question 1 - Select One
45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
A6 daysB8 daysC623 daysD734 days - Question 2 - Select One
Three men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
A1 daysB2 daysC3 daysD4 days - Question 3 - Select One or More
12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
A10 daysB12 daysC15 daysD9 days
12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution14 workers can make 1400 toys in 5 days. One day after they started the work 14 more workers joined them. How many days will they take to complete the remaining work ?
View Solution18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution24 men can complete a piece of work in 15 days. 2 days after
the 24 men started working, 4 men left the work. How
many more days will the remaining men now take to
complete the remaining work?View Solution