Doubtnut Promotions Sticky

14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?

A

12 days

B

7 days

C

9 days

D

None of these

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for 14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?

    A9 days
    B5 days
    C6 days
    D7 days
  • Question 2 - Select One

    Three men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?

    A1 days
    B2 days
    C3 days
    D4 days
  • Question 3 - Select One

    14 workers can make 1400 toys in 5 days. One day after they started the work 14 more workers joined them. How many days will they take to complete the remaining work ?

    A2 days
    B3 days
    C4 days
    D312 days