6 men and 4 women can do a piece of work in 32 days. 7 men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?
10
12
14
16
The correct Answer is:B
To solve the problem step by step, we will follow these steps:
Step 1: Define Variables
Let the efficiency of one man be x and the efficiency of one woman be y.
Step 2: Calculate Total Work from the First Scenario
From the first scenario, we have:
- 6 men and 4 women can complete the work in 32 days.
The total work done can be expressed as:
Total Work=Efficiency×Days
Thus, the total work done by 6 men and 4 women in 32 days is:
6x+4y (efficiency per day)×32 (days)=32(6x+4y)
Step 3: Calculate Total Work from the Second Scenario
From the second scenario, we have:
- 7 men and 12 women can complete the work in 18 days.
The total work done in this case is:
7x+12y (efficiency per day)×18 (days)=18(7x+12y)
Step 4: Set the Equations Equal
Since both expressions represent the total work, we can set them equal to each other:
32(6x+4y)=18(7x+12y)
Step 5: Expand and Simplify
Expanding both sides:
192x+128y=126x+216y
Rearranging gives:
192x−126x=216y−128y
66x=88y
Step 6: Solve for the Ratio of Efficiencies
Dividing both sides by 22:
3x=4y⇒xy=43
Step 7: Express Efficiencies in Terms of a Common Variable
Let x=4k and y=3k for some constant k.
Step 8: Calculate Total Work Using Either Scenario
Using the first scenario to find total work:
Total Work=32(6x+4y)=32(6(4k)+4(3k))=32(24k+12k)=32(36k)=1152k
Step 9: Calculate Work Done by 18 Men and 8 Women
Now, we need to find out how many days t it takes for 18 men and 8 women to complete the same work:
Efficiency of 18 men and 8 women=18x+8y=18(4k)+8(3k)=72k+24k=96k
Step 10: Set Up the Equation for Total Work
Setting up the equation:
96k⋅t=1152k
Step 11: Solve for t
Dividing both sides by 96k:
t=1152k96k=12
Conclusion
Thus, 18 men and 8 women can complete the work together in 12 days.
---
Let the efficiency of one man be x and the efficiency of one woman be y.
From the first scenario, we have:
- 6 men and 4 women can complete the work in 32 days.
Total Work=Efficiency×Days
Thus, the total work done by 6 men and 4 women in 32 days is:
6x+4y (efficiency per day)×32 (days)=32(6x+4y)
From the second scenario, we have:
- 7 men and 12 women can complete the work in 18 days.
7x+12y (efficiency per day)×18 (days)=18(7x+12y)
Since both expressions represent the total work, we can set them equal to each other:
32(6x+4y)=18(7x+12y)
Expanding both sides:
192x+128y=126x+216y
192x−126x=216y−128y
66x=88y
Dividing both sides by 22:
3x=4y⇒xy=43
Let x=4k and y=3k for some constant k.
Using the first scenario to find total work:
Total Work=32(6x+4y)=32(6(4k)+4(3k))=32(24k+12k)=32(36k)=1152k
Now, we need to find out how many days t it takes for 18 men and 8 women to complete the same work:
Efficiency of 18 men and 8 women=18x+8y=18(4k)+8(3k)=72k+24k=96k
Setting up the equation:
96k⋅t=1152k
Dividing both sides by 96k:
t=1152k96k=12
Thus, 18 men and 8 women can complete the work together in 12 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)
20 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
Knowledge Check
Six men and 4 women can do a piece of work in 32 days. Seven men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?
A10B12C14D166 men and 4 women can do a piece of work in 32 days. 7 men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?
A10B12C14D16Six men and 4 women can do a piece of work in 32 days. Seven men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?
A10B12C14D16
6 men and 9 women can do a piece of work in 4 days.4 men and 3 women can do it in 8 days. In how many days can 20 men and 6 women do the same work ?
View Solution6 men and 9 women can do a piece of work in 4 days.4 men and 3 women can do it in 8 days. In how many days can 20 men and 6 women do the same work ?
View Solution6 men and 9 women can do a piece of work in 4 days.4 men and 3 women can do it in 8 days. In how many days can 20 men and 6 women do the same work ?
View Solution2 men and 7 women can do a piece of work in 14 days whereas 3 men and 8 women can do it in 11 days. In how many days 5 men and 4 women can do the same work?
View Solution5 men can do a piece of work in 6 days while 10 women can do it in 5 days. In how many days can 5 women and 3 men do it?
View Solution