Malini can do a piece of work in 20 days, while Shalini can do it in 25 days. Shalini started the work and after 5 days Malini joined her.They together completed the remaining work. How ,many days did they take to complete the whole work?
818
8
889
1389
The correct Answer is:D
To solve the problem step by step, we will first determine the work done by Malini and Shalini individually, then calculate the work done by Shalini in the first 5 days, and finally find out how long it takes for both of them to complete the remaining work together.
Step 1: Determine the work done by Malini and Shalini in one day.
- Malini can complete the work in 20 days. Therefore, her one day work is:
Malini's one day work=120 of the work
- Shalini can complete the work in 25 days. Therefore, her one day work is:
Shalini's one day work=125 of the work
Step 2: Calculate the total work done by each in one day.
To make calculations easier, let's consider the total work as 100 units.
- Malini's one day work:
Malini's one day work=10020=5 units
- Shalini's one day work:
Shalini's one day work=10025=4 units
Step 3: Calculate the work done by Shalini in the first 5 days.
Since Shalini works alone for the first 5 days:
Work done by Shalini in 5 days=5×4=20 units
Step 4: Calculate the remaining work after 5 days.
The total work is 100 units, and Shalini has completed 20 units. Therefore, the remaining work is:
Remaining work=100−20=80 units
Step 5: Calculate the combined work done by Malini and Shalini in one day.
When Malini joins Shalini, they work together:
Combined one day work=Malini's one day work+Shalini's one day work=5+4=9 units
Step 6: Calculate the number of days required to complete the remaining work.
To find out how many days they need to finish the remaining 80 units:
Days required=Remaining workCombined one day work=809≈8.89 days or 889 days
Step 7: Calculate the total time taken to complete the work.
The total time taken is the time Shalini worked alone plus the time they worked together:
Total time=5 days+809 days=5+889=1389 days
Final Answer:
Thus, the total number of days taken to complete the whole work is:
Total days=1389 days
---
- Malini can complete the work in 20 days. Therefore, her one day work is:
Malini's one day work=120 of the work
- Shalini can complete the work in 25 days. Therefore, her one day work is:
Shalini's one day work=125 of the work
To make calculations easier, let's consider the total work as 100 units.
- Malini's one day work:
Malini's one day work=10020=5 units
- Shalini's one day work:
Shalini's one day work=10025=4 units
Since Shalini works alone for the first 5 days:
Work done by Shalini in 5 days=5×4=20 units
The total work is 100 units, and Shalini has completed 20 units. Therefore, the remaining work is:
Remaining work=100−20=80 units
When Malini joins Shalini, they work together:
Combined one day work=Malini's one day work+Shalini's one day work=5+4=9 units
To find out how many days they need to finish the remaining 80 units:
Days required=Remaining workCombined one day work=809≈8.89 days or 889 days
The total time taken is the time Shalini worked alone plus the time they worked together:
Total time=5 days+809 days=5+889=1389 days
Thus, the total number of days taken to complete the whole work is:
Total days=1389 days
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question5videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK PIPES AND CISTERNS
Similar Questions
A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View Solution
Knowledge Check
- Question 1 - Select One
Malini can do a piece of work in 20 days, while Shalini can do it in 25 days. Shalini started the work and after 5 days Malini joined her.They together completed the remaining work. How ,many days did they take to complete the whole work?
A818B8C889D1398 - Question 2 - Select One
A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
A70 daysB4234 daysC2717daysD1717 days - Question 3 - Select One
Raja can do a piece of work in 20 days while Ramesh can finish it In 25 days. Ramesh started working and Raja joined him after 10 days. The whole work is completed in
A18 daysB1623 daysC20 daysD15 days
A can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View SolutionA can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionA can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?
View SolutionA and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View Solution