Doubtnut Promotions Sticky

Malini can do a piece of work in 20 days, while Shalini can do it in 25 days. Shalini started the work and after 5 days Malini joined her.They together completed the remaining work. How ,many days did they take to complete the whole work?

A

818

B

8

C

889

D

1389

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the work done by Malini and Shalini individually, then calculate the work done by Shalini in the first 5 days, and finally find out how long it takes for both of them to complete the remaining work together.

Step 1: Determine the work done by Malini and Shalini in one day.
- Malini can complete the work in 20 days. Therefore, her one day work is:
Malini's one day work=120 of the work
- Shalini can complete the work in 25 days. Therefore, her one day work is:
Shalini's one day work=125 of the work

Step 2: Calculate the total work done by each in one day.
To make calculations easier, let's consider the total work as 100 units.
- Malini's one day work:
Malini's one day work=10020=5 units
- Shalini's one day work:
Shalini's one day work=10025=4 units

Step 3: Calculate the work done by Shalini in the first 5 days.
Since Shalini works alone for the first 5 days:
Work done by Shalini in 5 days=5×4=20 units

Step 4: Calculate the remaining work after 5 days.
The total work is 100 units, and Shalini has completed 20 units. Therefore, the remaining work is:
Remaining work=10020=80 units

Step 5: Calculate the combined work done by Malini and Shalini in one day.
When Malini joins Shalini, they work together:
Combined one day work=Malini's one day work+Shalini's one day work=5+4=9 units

Step 6: Calculate the number of days required to complete the remaining work.
To find out how many days they need to finish the remaining 80 units:
Days required=Remaining workCombined one day work=8098.89 days or 889 days

Step 7: Calculate the total time taken to complete the work.
The total time taken is the time Shalini worked alone plus the time they worked together:
Total time=5 days+809 days=5+889=1389 days

Final Answer:
Thus, the total number of days taken to complete the whole work is:
Total days=1389 days

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Malini can do a piece of work in 20 days, while Shalini can do it in 25 days. Shalini started the work and after 5 days Malini joined her.They together completed the remaining work. How ,many days did they take to complete the whole work?

    A818
    B8
    C889
    D1398
  • Question 2 - Select One

    A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    A70 days
    B4234 days
    C2717days
    D1717 days
  • Question 3 - Select One

    Raja can do a piece of work in 20 days while Ramesh can finish it In 25 days. Ramesh started working and Raja joined him after 10 days. The whole work is completed in

    A18 days
    B1623 days
    C20 days
    D15 days