Doubtnut Promotions Sticky

8 men can finish a piece of work in 40 days. If 2 more men join them, the work will be computed in (a)30 days (b) 32 days (c)36 days (d) 25 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Understand the Work Done by 8 Men
We know that 8 men can finish a piece of work in 40 days.

Step 2: Calculate the Work Done by 1 Man in 1 Day
To find out how much work 1 man can do in a day, we first calculate the total work done by 8 men in 40 days.

Total work can be expressed as:
Total Work=Number of Men×Days=8 men×40 days=320 man-days

Now, if 8 men complete 320 man-days of work in 40 days, then the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=320 man-days8 men×40 days=140 of the work

Step 3: Calculate Work Done by 10 Men in 1 Day
Now, if 2 more men join the original 8 men, we have a total of 10 men. The work done by 10 men in 1 day is:
Work done by 10 men in 1 day=10×1320=10320=132 of the work

Step 4: Calculate the Total Days Required for 10 Men
Let x be the number of days required for 10 men to complete the work. Since they complete 132 of the work in one day, the equation for total work becomes:
10 men×x days×132=1 (complete work)

This simplifies to:
10x32=1

Step 5: Solve for x
To find x, we can rearrange the equation:
10x=32
x=3210=3.2 days

Step 6: Calculate Total Days
Since we need the total number of days for 10 men to finish the work:
x=32 days

Conclusion
Thus, if 2 more men join the original 8 men, the work will be completed in 32 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    8 men can finish a work in 40 days .If 2 more men would join them ,then how much days will required to finish the work ?

    A30
    B32
    C36
    D25
  • Question 2 - Select One

    If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :

    A38
    B28
    C19
    D17
  • Question 3 - Select One

    If six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days

    A10
    B12
    C15
    D18