8 men can finish a piece of work in 40 days. If 2 more men join them, the work will be computed in (a)30 days (b) 32 days (c)36 days (d) 25 days
To solve the problem step by step, let's break it down:
Step 1: Understand the Work Done by 8 Men
We know that 8 men can finish a piece of work in 40 days.
Step 2: Calculate the Work Done by 1 Man in 1 Day
To find out how much work 1 man can do in a day, we first calculate the total work done by 8 men in 40 days.
Total work can be expressed as:
Total Work=Number of Men×Days=8 men×40 days=320 man-days
Now, if 8 men complete 320 man-days of work in 40 days, then the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=320 man-days8 men×40 days=140 of the work
Step 3: Calculate Work Done by 10 Men in 1 Day
Now, if 2 more men join the original 8 men, we have a total of 10 men. The work done by 10 men in 1 day is:
Work done by 10 men in 1 day=10×1320=10320=132 of the work
Step 4: Calculate the Total Days Required for 10 Men
Let x be the number of days required for 10 men to complete the work. Since they complete 132 of the work in one day, the equation for total work becomes:
10 men×x days×132=1 (complete work)
This simplifies to:
10x32=1
Step 5: Solve for x
To find x, we can rearrange the equation:
10x=32
x=3210=3.2 days
Step 6: Calculate Total Days
Since we need the total number of days for 10 men to finish the work:
x=32 days
Conclusion
Thus, if 2 more men join the original 8 men, the work will be completed in 32 days.
We know that 8 men can finish a piece of work in 40 days.
To find out how much work 1 man can do in a day, we first calculate the total work done by 8 men in 40 days.
Total Work=Number of Men×Days=8 men×40 days=320 man-days
Work done by 1 man in 1 day=320 man-days8 men×40 days=140 of the work
Now, if 2 more men join the original 8 men, we have a total of 10 men. The work done by 10 men in 1 day is:
Work done by 10 men in 1 day=10×1320=10320=132 of the work
Let x be the number of days required for 10 men to complete the work. Since they complete 132 of the work in one day, the equation for total work becomes:
10 men×x days×132=1 (complete work)
10x32=1
To find x, we can rearrange the equation:
10x=32
x=3210=3.2 days
Since we need the total number of days for 10 men to finish the work:
x=32 days
Thus, if 2 more men join the original 8 men, the work will be completed in 32 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
8 men can finish a work in 40 days .If 2 more men would join them ,then how much days will required to finish the work ?
A30B32C36D25 - Question 2 - Select One
If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
A38B28C19D17 - Question 3 - Select One
If six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days
A10B12C15D18
If 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?
View SolutionIf 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?
View Solution12 men can finish a piece of work in 25 days. The number of days in which the same piece of work can be done by 20 men, is (a) 10 days (b) 12 days (c) 15 days (d) 14 days
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution