Doubtnut Promotions Sticky

A and B do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?​

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work rates of A and B
- A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)

Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=120+115
- To add these fractions, we need a common denominator. The least common multiple of 20 and 15 is 60.
120=360,115=460
- Therefore,
Combined work rate=360+460=760 (work per day)

Step 3: Calculate the work done by A and B in 2 days
- In 2 days, the amount of work done by A and B together is:
Work done in 2 days=2×760=1460=730

Step 4: Determine the remaining work
- The total work is considered as 1 unit (whole work). Therefore, the remaining work after A and B work together for 2 days is:
Remaining work=1730=3030730=2330

Step 5: Calculate the time taken by B to finish the remaining work
- B's work rate is 115 work per day. To find the number of days B will take to finish 2330 of the work, we use the formula:
Time=Remaining workB's work rate=2330115
- This simplifies to:
Time=2330×15=23×1530=23×12=232=11.5 days

Final Answer
B will take 11.5 days to finish the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

    A17 days
    B11 days
    C10 days
    D15 days
  • Question 2 - Select One

    A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

    A17 1/2 days
    B11 days
    C8 4/7 days
    D10 days
  • Question 3 - Select One

    A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?

    A9 days
    B11 days
    C15 days
    D20 days