A and B together can do a piece of work in 8 days. B alone can do it in 12 days. B alone works at it for 4 days. In how many more days after that could A alone complete it.

A

15 days

B

18 days

C

16 days

D

20 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the information given in the question and use the concepts of work and efficiency.

Step 1: Determine the work done by A and B together
A and B together can complete the work in 8 days. Therefore, their combined work rate (efficiency) per day is:
Work rate of A + B=18 (work per day)

Step 2: Determine the work done by B alone
B alone can complete the work in 12 days. Therefore, B's work rate is:
Work rate of B=112 (work per day)

Step 3: Calculate the work done by A alone
Let A's work rate be 1x (where x is the number of days A takes to complete the work alone). We know that:
Work rate of A + Work rate of B=Work rate of A + B
Thus,
1x+112=18

Step 4: Solve for A's work rate
To solve for 1x, we rearrange the equation:
1x=18112
Finding a common denominator (which is 24):
18=324,112=224
So,
1x=324224=124
Thus, A's work rate is:
x=24 days

Step 5: Calculate the total work done by B in 4 days
Now, we need to find out how much work B does in 4 days:
Work done by B in 4 days=4×112=412=13

Step 6: Calculate the remaining work
The total work is considered as 1 unit. Therefore, the remaining work after B has worked for 4 days is:
Remaining work=113=23

Step 7: Calculate the time taken by A to complete the remaining work
Now, we need to find out how long it will take A to complete the remaining 23 of the work:
Time=WorkEfficiency=23124=23×24=16 days

Final Answer
A alone can complete the remaining work in 16 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can do a piece of work in 5 days and A alone can do it in 30 days. B alone can do the work in how many days?

    A5
    B6
    C8
    D10
  • A and B together can do a piece of work in 20 days and A alone can do it in 30 days. B alone can do the work in how many days?

    Aa)45
    Bb)60
    Cc)75
    Dd)90
  • A and B together can do a piece of work in 40 days and A alone can do it in 60 days. B alone can do the work in how many days?

    A80
    B90
    C120
    D75