Doubtnut Promotions Sticky

A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

A

6 days

B

8 days

C

9 days

D

5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow these calculations:

Step 1: Calculate the work done by B and C together in one day.
- A can complete the work in 9 days, so A's work in one day = 19
- B can complete the work in 10 days, so B's work in one day = 110
- C can complete the work in 15 days, so C's work in one day = 115

Now, we need to find the combined work of B and C in one day:
Work of B + Work of C=110+115
To add these fractions, we need a common denominator. The least common multiple (LCM) of 10 and 15 is 30.

Converting the fractions:
110=330,115=230
Now add them:
330+230=530=16
Thus, B and C together can complete 16 of the work in one day.

Step 2: Calculate the work done by B and C in 2 days.
Since B and C work together for 2 days:
Work done in 2 days=2×16=26=13
So, B and C complete 13 of the work in 2 days.

Step 3: Calculate the remaining work.
The total work is considered as 1 (whole work). Therefore, the remaining work after B and C have worked for 2 days is:
Remaining work=113=23

Step 4: Calculate the time taken by A to complete the remaining work.
A can complete the whole work in 9 days, which means A's work rate is 19 of the work in one day. To find out how many days A will take to complete 23 of the work, we set up the equation:
Time taken by A=Remaining work÷A's work rate=23÷19
This can be simplified as:
23×9=2×93=183=6
Thus, A will take 6 days to complete the remaining work.

Final Answer:
A will take 6 days to complete the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B9 days
    C10 days
    D13 days
  • Question 2 - Select One

    A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16
  • Question 3 - Select One

    A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

    A10 days
    B12 days
    C15 days
    D16 days