A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
6 days
8 days
9 days
5 days
The correct Answer is:A
To solve the problem step by step, we will follow these calculations:
Step 1: Calculate the work done by B and C together in one day.
- A can complete the work in 9 days, so A's work in one day = 19
- B can complete the work in 10 days, so B's work in one day = 110
- C can complete the work in 15 days, so C's work in one day = 115
Now, we need to find the combined work of B and C in one day:
Work of B + Work of C=110+115
To add these fractions, we need a common denominator. The least common multiple (LCM) of 10 and 15 is 30.
Converting the fractions:
110=330,115=230
Now add them:
330+230=530=16
Thus, B and C together can complete 16 of the work in one day.
Step 2: Calculate the work done by B and C in 2 days.
Since B and C work together for 2 days:
Work done in 2 days=2×16=26=13
So, B and C complete 13 of the work in 2 days.
Step 3: Calculate the remaining work.
The total work is considered as 1 (whole work). Therefore, the remaining work after B and C have worked for 2 days is:
Remaining work=1−13=23
Step 4: Calculate the time taken by A to complete the remaining work.
A can complete the whole work in 9 days, which means A's work rate is 19 of the work in one day. To find out how many days A will take to complete 23 of the work, we set up the equation:
Time taken by A=Remaining work÷A's work rate=23÷19
This can be simplified as:
23×9=2×93=183=6
Thus, A will take 6 days to complete the remaining work.
Final Answer:
A will take 6 days to complete the remaining work.
---
- A can complete the work in 9 days, so A's work in one day = 19
- B can complete the work in 10 days, so B's work in one day = 110
- C can complete the work in 15 days, so C's work in one day = 115
Work of B + Work of C=110+115
To add these fractions, we need a common denominator. The least common multiple (LCM) of 10 and 15 is 30.
110=330,115=230
Now add them:
330+230=530=16
Thus, B and C together can complete 16 of the work in one day.
Since B and C work together for 2 days:
Work done in 2 days=2×16=26=13
So, B and C complete 13 of the work in 2 days.
The total work is considered as 1 (whole work). Therefore, the remaining work after B and C have worked for 2 days is:
Remaining work=1−13=23
A can complete the whole work in 9 days, which means A's work rate is 19 of the work in one day. To find out how many days A will take to complete 23 of the work, we set up the equation:
Time taken by A=Remaining work÷A's work rate=23÷19
This can be simplified as:
23×9=2×93=183=6
Thus, A will take 6 days to complete the remaining work.
A will take 6 days to complete the remaining work.
Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 13(b)
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- SIMPLE INTEREST BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMPLE INTEREST EXERCISE - Self Assessment Sheet
10 Videos
- TRIANGLESBOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLESEXERCISE - Self Assessment Sheet - 18
10 Videos
Similar Questions
A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA can complete a piece of work In 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View Solution
Knowledge Check
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A6 daysB9 daysC10 daysD13 daysA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
A10B12C15D16A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
A10 daysB12 daysC15 daysD16 days
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionRam and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:
View SolutionA and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :
View SolutionA and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :
View SolutionA can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
View Solution