Doubtnut Promotions Sticky

A, B and C can complete a work in 2h. If A does the job alone in 6h and B in 5h, how long will it take for C to finish the job alone ?

A

512h

B

712h

C

9 h

D

412h

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B


Let C alone can finish the job in x h According to the questions,
Work done by A, B and c in 1 h = 12
16+15+1x=12
1x=121615=155630
=430=215
x=712h

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a work in 2h. If A does the job alone in 6h and B in 5h, how long will it take for C to finish the job alone ?

    A512h
    B712h
    C9 h
    D412h
  • Question 2 - Select One

    How long will it take C to finish the work alone?

    A30 days
    B22 days
    C452days
    D25 days
  • Question 3 - Select One

    A and C can finish a work in 40 days. They worked at it for 10 days and then A left. The remaining work is done by C alone in 30 more days. How long will it take C to finish the work alone?

    A30 days
    B22 days
    C40 days
    D25 days