A completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
3.8 days
3.33 days
2.22 days
4.3 days
The correct Answer is:B
To solve the problem step by step, we will first determine the work rates of A, B, and C, then calculate the total work done when they work together, and finally find out how long it takes for B to finish the remaining work alone.
Step 1: Calculate the total time taken by A, B, and C to complete the entire job.
1. A's work rate:
- A completes 23 of the job in 6 days.
- Therefore, to complete the entire job, A would take:
Total time for A=6×32=9 days
2. B's work rate:
- B completes 13 of the job in 8 days.
- Therefore, to complete the entire job, B would take:
Total time for B=8×3=24 days
3. C's work rate:
- C completes 34 of the job in 12 days.
- Therefore, to complete the entire job, C would take:
Total time for C=12×43=16 days
Step 2: Calculate the work done by A, B, and C in one day.
1. A's work per day:
A's work per day=19 of the job
2. B's work per day:
B's work per day=124 of the job
3. C's work per day:
C's work per day=116 of the job
Step 3: Calculate the total work done by A, B, and C together in 4 days.
1. Combined work rate:
Combined work rate=A's work per day+B's work per day+C's work per day
=19+124+116
To add these fractions, find a common denominator. The least common multiple (LCM) of 9, 24, and 16 is 144.
- Convert each fraction:
19=16144,124=6144,116=9144
- Now add them:
Combined work rate=16+6+9144=31144
2. Work done in 4 days:
Work done in 4 days=Combined work rate×4=31144×4=124144=3136 of the job
Step 4: Calculate the remaining work.
1. Remaining work:
Remaining work=1−3136=536 of the job
Step 5: Calculate how long it will take for B to complete the remaining work alone.
1. B's work rate:
B's work per day=124 of the job
2. Time taken by B to complete the remaining work:
Time=Remaining workB's work per day=536124=536×24=12036=103 days≈3.33 days
Final Answer:
B will take approximately 3.33 days to complete the remaining work alone.
---
- A completes 23 of the job in 6 days.
- Therefore, to complete the entire job, A would take:
Total time for A=6×32=9 days
- B completes 13 of the job in 8 days.
- Therefore, to complete the entire job, B would take:
Total time for B=8×3=24 days
- C completes 34 of the job in 12 days.
- Therefore, to complete the entire job, C would take:
Total time for C=12×43=16 days
A's work per day=19 of the job
B's work per day=124 of the job
C's work per day=116 of the job
Combined work rate=A's work per day+B's work per day+C's work per day
=19+124+116
19=16144,124=6144,116=9144
Combined work rate=16+6+9144=31144
Work done in 4 days=Combined work rate×4=31144×4=124144=3136 of the job
Remaining work=1−3136=536 of the job
B's work per day=124 of the job
Time=Remaining workB's work per day=536124=536×24=12036=103 days≈3.33 days
B will take approximately 3.33 days to complete the remaining work alone.
Topper's Solved these Questions
Similar Questions
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
A6B214C812D9 - Question 2 - Select One
A can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?
A9 daysB6 daysC4 daysD5 days - Question 3 - Select One
A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is
A16B32C64D128
A completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?
View SolutionA can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
View SolutionA' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
View Solution‘A’ completes a work in 12 days. ‘B’ completes the same work in 15 days. ‘A’ started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
View SolutionIf A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.
View Solution