Doubtnut Promotions Sticky

A completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?

A

3.8 days

B

3.33 days

C

2.22 days

D

4.3 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work rates of A, B, and C, then calculate the total work done when they work together, and finally find out how long it takes for B to finish the remaining work alone.

Step 1: Calculate the total time taken by A, B, and C to complete the entire job.

1. A's work rate:
- A completes 23 of the job in 6 days.
- Therefore, to complete the entire job, A would take:
Total time for A=6×32=9 days

2. B's work rate:
- B completes 13 of the job in 8 days.
- Therefore, to complete the entire job, B would take:
Total time for B=8×3=24 days

3. C's work rate:
- C completes 34 of the job in 12 days.
- Therefore, to complete the entire job, C would take:
Total time for C=12×43=16 days

Step 2: Calculate the work done by A, B, and C in one day.

1. A's work per day:
A's work per day=19 of the job

2. B's work per day:
B's work per day=124 of the job

3. C's work per day:
C's work per day=116 of the job

Step 3: Calculate the total work done by A, B, and C together in 4 days.

1. Combined work rate:
Combined work rate=A's work per day+B's work per day+C's work per day
=19+124+116

To add these fractions, find a common denominator. The least common multiple (LCM) of 9, 24, and 16 is 144.

- Convert each fraction:
19=16144,124=6144,116=9144

- Now add them:
Combined work rate=16+6+9144=31144

2. Work done in 4 days:
Work done in 4 days=Combined work rate×4=31144×4=124144=3136 of the job

Step 4: Calculate the remaining work.

1. Remaining work:
Remaining work=13136=536 of the job

Step 5: Calculate how long it will take for B to complete the remaining work alone.

1. B's work rate:
B's work per day=124 of the job

2. Time taken by B to complete the remaining work:
Time=Remaining workB's work per day=536124=536×24=12036=103 days3.33 days

Final Answer:
B will take approximately 3.33 days to complete the remaining work alone.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

    A6
    B214
    C812
    D9
  • Question 2 - Select One

    A can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

    A9 days
    B6 days
    C4 days
    D5 days
  • Question 3 - Select One

    A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

    A16
    B32
    C64
    D128