A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
6
8
5
4
The correct Answer is:C
Step by step video, text & image solution for A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ? by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.
Topper's Solved these Questions
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - AVERAGE EXERCISE - SELF ASSESSMENT SHEET -1610videos
AVERAGE
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - ALGEBRIC IDENTITIESEXERCISE - Self Assessment Sheet-710videos
ALGEBRIC IDENTITIES
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - CIRCLES EXERCISE - UNIT TEST20videos
CIRCLES
Similar Questions
45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
- Question 1 - Select One
A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
A6B8C5D4 - Question 2 - Select One
A completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?
A8 daysB7 daysC6 daysDNone of these - Question 3 - Select One
P can complete a work in 15 days.Q can complete the same work in 10 days ,P started working and after 5 days Q joined him. How many days more will they take to complete the remaining work ?
A1 daysB2 daysC3 daysD4 days
45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution