A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?

A

6

B

8

C

5

D

4

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we can follow these instructions:

Step 1: Determine the work done by A and B in one day.
- A completes the work in 12 days, so A's work in one day is:
Work done by A in 1 day=112
- B completes the work in 15 days, so B's work in one day is:
Work done by B in 1 day=115

Hint: To find the work done in one day, take the reciprocal of the number of days taken to complete the work.

Step 2: Calculate the work done by A in the first 3 days.
- In 3 days, A will complete:
Work done by A in 3 days=3×112=312=14

Hint: Multiply the work done in one day by the number of days worked to find the total work done.

Step 3: Determine the remaining work after A has worked for 3 days.
- The total work is considered as 1 (whole work). Therefore, the remaining work after A has worked for 3 days is:
Remaining work=114=34

Hint: Subtract the work done from the total work to find the remaining work.

Step 4: Calculate the combined work done by A and B in one day.
- When A and B work together, their combined work in one day is:
Combined work=112+115
- To add these fractions, find the least common multiple (LCM) of 12 and 15, which is 60:
112=560,115=460
- Therefore,
Combined work=560+460=960=320

Hint: To add fractions, convert them to have a common denominator.

Step 5: Calculate the number of days required to complete the remaining work.
- Let X be the number of days required to finish the remaining work of 34:
X×320=34
- To find X, solve the equation:
X=3/43/20=34×203=204=5

Hint: To isolate X, divide the remaining work by the combined work done in one day.

Conclusion
- A and B together will take 5 days to complete the remaining work.

Final Answer: 5 days

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?

    A6
    B8
    C5
    D4
  • A completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?

    A8 days
    B7 days
    C6 days
    DNone of these
  • P can complete a work in 15 days.Q can complete the same work in 10 days ,P started working and after 5 days Q joined him. How many days more will they take to complete the remaining work ?

    A1 days
    B2 days
    C3 days
    D4 days