A constrator employed 210 men to build a house in 60 days. After 12 days.he was joined by 70 more men. In how many days will the remaining work be finished?
Hint. 210 men can complete the remaning work in 48 days.Find in how many days 280 men can do it.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:36 days


To solve the problem step by step, we will follow the hints provided and use the unitary method.

Step 1: Calculate the total work done by 210 men in 12 days.
- Total work can be represented in terms of man-days.
- If 210 men can complete the work in 60 days, the total work is:
Total Work=210 men×60 days=12600 man-days

Step 2: Calculate the work done in the first 12 days.
- In 12 days, the work done by 210 men is:
Work done in 12 days=210 men×12 days=2520 man-days

Step 3: Calculate the remaining work.
- The remaining work after 12 days is:
Remaining Work=Total WorkWork done in 12 days
Remaining Work=12600 man-days2520 man-days=10080 man-days

Step 4: Determine the new workforce.
- After 12 days, 70 more men join the original 210 men, making the total number of men:
Total Men=210+70=280 men

Step 5: Calculate the time taken by 280 men to complete the remaining work.
- If 280 men are working, we need to find out how many days it will take to complete 10080 man-days of work:
Days=Remaining WorkTotal Men=10080 man-days280 men=36 days

Final Answer:
The remaining work will be finished in 36 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?

    A18
    B12
    C24
    DCannot be determined
  • If 45 men can do a piece of work in 49 days, in how many days will 35 men do it?

    A63
    B53
    C43
    D33
  • 45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?

    A10
    B16
    C18
    D15