A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
The correct Answer is:12 days
Step by step video, text & image solution for A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Topper's Solved these Questions
- BOOK - NAGEEN PRAKASHANCHAPTER - QUADRATIC EQUATIONSEXERCISE - Revision Exercise Very Short Answer Questions15videos
QUADRATIC EQUATIONS
- BOOK - NAGEEN PRAKASHANCHAPTER - QUADRATIC EQUATIONSEXERCISE - Revision Exercise Short Answer Questions10videos
QUADRATIC EQUATIONS
- BOOK - NAGEEN PRAKASHANCHAPTER - QUADRATIC EQUATIONSEXERCISE - Exercise 4c12videos
QUADRATIC EQUATIONS
- BOOK - NAGEEN PRAKASHANCHAPTER - PROBABILITYEXERCISE - Revision Exercise Very Short Answer/short Answer Questions16videos
PROBABILITY
- BOOK - NAGEEN PRAKASHANCHAPTER - REAL NUMBERSEXERCISE - Revision Exercise Long Answer Questions5videos
REAL NUMBERS
Similar Questions
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View SolutionA takes 10 days less than the time taken by B to finish a piece of work. If both A and 6 can do it in 12 days, then the time taken by B alone to finish the work is
View Solution
Knowledge Check
- Question 1 - Select One
X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?A30 daysB27 daysC20 daysD25 days - Question 2 - Select One
When A alone does a piece of work , he takes 25 days more than the time taken (A+B) to completes that particular work, while B alone takes 49 days more than the time taken by (A + B) to finish the same work. A andBtogether will take what time to finish this work?
A35 daysB25 daysC15 daysD45 days
2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.
View SolutionWhen A alone does a piece of work , he takes 16 days more than the time taken by (A+B) to complete the work, while B alone takes 9 days more than the time taken by (A + B) to finish the work. What time,AandBtogether will take to finish this work?
View Solution4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days , then the time taken by one man alone is
View SolutionA can do a work in 5 days less than the time taken by B to do it. If both of them together take 1119days, then the time taken by B alone to the same work (in days) is
View Solution2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the work, and also that taken by 1 man alone.
View SolutionA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?
View Solution