Doubtnut Promotions Sticky

A takes 10 days less than the time taken by B to finish a piece of work. If both A and 6 can do it in 12 days, then the time taken by B alone to finish the work is

A

(a)30 days

B

(b)27 days

C

(c)20 days

D

(d)25 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to find out how long it takes for B to finish the work alone, given that A takes 10 days less than B and that together they can complete the work in 12 days.

1. Define Variables:
Let the time taken by B to finish the work alone be x days.
Therefore, the time taken by A to finish the work alone will be x10 days.

2. Calculate Work Rates:
The work done by A in one day is 1x10 and the work done by B in one day is 1x.

3. Combined Work Rate:
When A and B work together, their combined work rate is:
1x10+1x

4. Set Up the Equation:
Since A and B can complete the work together in 12 days, their combined work rate is also equal to 112. Therefore, we can set up the equation:
1x10+1x=112

5. Find a Common Denominator:
The common denominator for the left side is x(x10). Thus, we rewrite the equation:
x+(x10)x(x10)=112
Simplifying the numerator gives:
2x10x(x10)=112

6. Cross-Multiply:
Cross-multiplying gives:
12(2x10)=x(x10)

7. Expand and Rearrange:
Expanding both sides:
24x120=x210x
Rearranging gives:
x234x+120=0

8. Solve the Quadratic Equation:
To solve the quadratic equation x234x+120=0, we can use the quadratic formula:
x=b±b24ac2a
Here, a=1,b=34,c=120:
x=34±(34)24112021
x=34±11564802
x=34±6762
x=34±262
This gives us two possible solutions:
x=602=30andx=82=4

9. Choose the Valid Solution:
Since A takes x10 days, if x=30, then A takes 20 days, which is valid. If x=4, then A would take 6 days, which is not possible. Thus, the time taken by B alone to finish the work is:
30 days

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
    X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?

    A30 days
    B27 days
    C20 days
    D25 days
  • Question 2 - Select One

    A and B can do a piece of work in 6 days and A alone can do it in 9 days. In how many days can B alone do it?

    A18 days
    B15 days
    C12 days
    D712 days
  • Question 3 - Select One

    A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A9
    B8
    C10
    D6