A takes 10 days less than the time taken by B to finish a piece of work. If both A and 6 can do it in 12 days, then the time taken by B alone to finish the work is
(a)30 days
(b)27 days
(c)20 days
(d)25 days
To solve the problem, we need to find out how long it takes for B to finish the work alone, given that A takes 10 days less than B and that together they can complete the work in 12 days.
1. Define Variables:
Let the time taken by B to finish the work alone be x days.
Therefore, the time taken by A to finish the work alone will be x−10 days.
2. Calculate Work Rates:
The work done by A in one day is 1x−10 and the work done by B in one day is 1x.
3. Combined Work Rate:
When A and B work together, their combined work rate is:
1x−10+1x
4. Set Up the Equation:
Since A and B can complete the work together in 12 days, their combined work rate is also equal to 112. Therefore, we can set up the equation:
1x−10+1x=112
5. Find a Common Denominator:
The common denominator for the left side is x(x−10). Thus, we rewrite the equation:
x+(x−10)x(x−10)=112
Simplifying the numerator gives:
2x−10x(x−10)=112
6. Cross-Multiply:
Cross-multiplying gives:
12(2x−10)=x(x−10)
7. Expand and Rearrange:
Expanding both sides:
24x−120=x2−10x
Rearranging gives:
x2−34x+120=0
8. Solve the Quadratic Equation:
To solve the quadratic equation x2−34x+120=0, we can use the quadratic formula:
x=−b±√b2−4ac2a
Here, a=1,b=−34,c=120:
x=34±√(−34)2−4⋅1⋅1202⋅1
x=34±√1156−4802
x=34±√6762
x=34±262
This gives us two possible solutions:
x=602=30andx=82=4
9. Choose the Valid Solution:
Since A takes x−10 days, if x=30, then A takes 20 days, which is valid. If x=4, then A would take −6 days, which is not possible. Thus, the time taken by B alone to finish the work is:
30 days
Let the time taken by B to finish the work alone be x days.
Therefore, the time taken by A to finish the work alone will be x−10 days.
The work done by A in one day is 1x−10 and the work done by B in one day is 1x.
When A and B work together, their combined work rate is:
1x−10+1x
Since A and B can complete the work together in 12 days, their combined work rate is also equal to 112. Therefore, we can set up the equation:
1x−10+1x=112
The common denominator for the left side is x(x−10). Thus, we rewrite the equation:
x+(x−10)x(x−10)=112
Simplifying the numerator gives:
2x−10x(x−10)=112
Cross-multiplying gives:
12(2x−10)=x(x−10)
Expanding both sides:
24x−120=x2−10x
Rearranging gives:
x2−34x+120=0
To solve the quadratic equation x2−34x+120=0, we can use the quadratic formula:
x=−b±√b2−4ac2a
Here, a=1,b=−34,c=120:
x=34±√(−34)2−4⋅1⋅1202⋅1
x=34±√1156−4802
x=34±√6762
x=34±262
This gives us two possible solutions:
x=602=30andx=82=4
Since A takes x−10 days, if x=30, then A takes 20 days, which is valid. If x=4, then A would take −6 days, which is not possible. Thus, the time taken by B alone to finish the work is:
30 days
Similar Questions
A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
View SolutionA takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View Solution
Knowledge Check
- Question 1 - Select One
X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?A30 daysB27 daysC20 daysD25 days - Question 2 - Select One
A and B can do a piece of work in 6 days and A alone can do it in 9 days. In how many days can B alone do it?
A18 daysB15 daysC12 daysD712 days - Question 3 - Select One
A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6
A can do a work in 5 days less than the time taken by B to do it. If both of them together take 1119days, then the time taken by B alone to the same work (in days) is
View SolutionWhen A alone does a piece of work , he takes 16 days more than the time taken by (A+B) to complete the work, while B alone takes 9 days more than the time taken by (A + B) to finish the work. What time,AandBtogether will take to finish this work?
View Solution2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.
View SolutionA is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is
View Solution4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days , then the time taken by one man alone is
View Solution