A takes 6 hours less than B to complete a work. If together they complete the work in 13 hours 20 minutes, find how much time will B alone take to complete the work.
To solve the problem, we need to find out how much time B alone will take to complete the work, given that A takes 6 hours less than B and they together complete the work in 13 hours and 20 minutes.
1. Convert the time they take together into hours:
13 hours 20 minutes=13+2060=13+13=403 hours
Hint: Always convert mixed time formats into a single unit (hours or minutes) for easier calculations.
2. Let the time taken by B to complete the work alone be x hours.
Then, the time taken by A to complete the work alone will be x−6 hours.
Hint: Define variables for the unknowns in the problem to make equations easier to set up.
3. Set up the equation based on their work rates:
The work done by A in one hour is 1x−6 and the work done by B in one hour is 1x. Together, they complete the work in 403 hours, so:
1x−6+1x=340
Hint: Use the concept of work rates to set up the equation; the sum of their rates equals the rate at which they work together.
4. Combine the fractions:
x+(x−6)x(x−6)=340
Simplifying the left side gives:
2x−6x(x−6)=340
Hint: When combining fractions, ensure you have a common denominator and simplify where possible.
5. Cross-multiply to eliminate the fractions:
40(2x−6)=3x(x−6)
Expanding both sides:
80x−240=3x2−18x
Hint: Cross-multiplication is a powerful tool for solving equations involving fractions.
6. Rearranging the equation:
3x2−18x−80x+240=0
This simplifies to:
3x2−98x+240=0
Hint: Always rearrange your equation to set it to zero, which is the standard form of a quadratic equation.
7. Use the quadratic formula to solve for x:
The quadratic formula is given by:
x=−b±√b2−4ac2a
Here, a=3, b=−98, and c=240.
x=−(−98)±√(−98)2−4⋅3⋅2402⋅3
x=98±√9604−28806
x=98±√67246
x=98±826
Hint: The quadratic formula allows you to find the roots of any quadratic equation, so it's a valuable tool.
8. Calculate the two possible values for x:
x=1806=30andx=166=83
Hint: Always check both solutions to see if they are valid in the context of the problem.
9. Determine the valid solution:
Since x represents the time taken by B, it must be a positive value. The value 83 hours (which is approximately 2.67 hours) would make A's time negative, which is not possible. Therefore, we take:
x=30 hours
Hint: Discard any solutions that do not make sense in the context of the problem.
Final Answer:
B alone will take 30 hours to complete the work.
13 hours 20 minutes=13+2060=13+13=403 hours
Then, the time taken by A to complete the work alone will be x−6 hours.
The work done by A in one hour is 1x−6 and the work done by B in one hour is 1x. Together, they complete the work in 403 hours, so:
1x−6+1x=340
x+(x−6)x(x−6)=340
Simplifying the left side gives:
2x−6x(x−6)=340
40(2x−6)=3x(x−6)
Expanding both sides:
80x−240=3x2−18x
3x2−18x−80x+240=0
This simplifies to:
3x2−98x+240=0
The quadratic formula is given by:
x=−b±√b2−4ac2a
Here, a=3, b=−98, and c=240.
x=−(−98)±√(−98)2−4⋅3⋅2402⋅3
x=98±√9604−28806
x=98±√67246
x=98±826
x=1806=30andx=166=83
Since x represents the time taken by B, it must be a positive value. The value 83 hours (which is approximately 2.67 hours) would make A's time negative, which is not possible. Therefore, we take:
x=30 hours
B alone will take 30 hours to complete the work.
Topper's Solved these Questions
- BOOK - NAGEEN PRAKASHANCHAPTER - QUADRATIC EQUATIONSEXERCISE - Problems From NCERT /exemplar17videos
QUADRATIC EQUATIONS
- BOOK - NAGEEN PRAKASHANCHAPTER - QUADRATIC EQUATIONSEXERCISE - Exercise 4a37videos
QUADRATIC EQUATIONS
- BOOK - NAGEEN PRAKASHANCHAPTER - PROBABILITYEXERCISE - Revision Exercise Very Short Answer/short Answer Questions16videos
PROBABILITY
- BOOK - NAGEEN PRAKASHANCHAPTER - REAL NUMBERSEXERCISE - Revision Exercise Long Answer Questions5videos
REAL NUMBERS
Similar Questions
Time taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
View SolutionA alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
A takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is
A15B12C10D9 - Question 2 - Select One
If A can complete a work in 80 min and B can complete the same work in 40 min. Then in how much time A and B together can complete the work.
AA)26 min 20 secondsBB)26 min 40 secondsCC)25 min 40 secondsDD)28 min 40 seconds - Question 3 - Select One
A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
A18 daysB24 daysC16 daysD20 days
B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.
View SolutionA takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work
View SolutionIf A & B completed a work together in 6 days . If A completed the same work in 10 days alone . Then in how many days will B complete the same work alone ?
View SolutionThe efficiencies of A,B and C are in the ratio 5 : 6 : 8, working together, they can complete a piece of work in 120 hours. In how many hours will, B alone be able to complete 40% of that work?
A, B तथा C की कार्य क्षमता 5 : 6: 8 के अनुपात में है | एक साथ कार्य करते हुए वे किसी कार्य को 120 घंटों में समाप्त कर सकते हैं | इस कार्य का 40% भाग पूरा करने में B को अकेले कितने घंटे लगेंगे ?View SolutionTo complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it ?
View Solution