A takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work
The correct Answer is: days, days, days
To solve the problem step by step, we will first define the efficiencies of A, B, and C based on the information provided in the question.
Step 1: Define the relationships between A, B, and C
1. Let the time taken by B and C together to complete the work be x days.
2. According to the problem, A takes three times as long as B and C together, so A takes 3x days.
3. The efficiency of A is 13x and the efficiency of B + C is 1x.
Step 2: Define the time taken by B
1. Let the time taken by A + C together be y days.
2. According to the problem, B takes four times as long as A + C together, so B takes 4y days.
3. The efficiency of B is 14y and the efficiency of A + C is 1y.
Step 3: Set up the equations
1. From the efficiencies, we have:
- Efficiency of A = 13x
- Efficiency of B + C = 1x
- Efficiency of B = 14y
- Efficiency of A + C = 1y
Step 4: Relate the efficiencies
1. Since B + C = A + C + B, we can express the efficiencies:
- Efficiency of A + B + C = Efficiency of A + Efficiency of B + Efficiency of C
- From the given information, we know that A takes 3 times as long as B + C, and B takes 4 times as long as A + C.
Step 5: Calculate the total efficiency
1. We know that A + B + C working together can complete the work in 22 days, which means their combined efficiency is 122.
2. Therefore, Efficiency of A+Efficiency of B+Efficiency of C=122.
Step 6: Solve for individual efficiencies
1. Let’s assume the efficiencies of A, B, and C are a,b,c respectively.
2. From the relationships, we can derive:
- a=13b
- b=14c
3. Substitute these into the equation for total efficiency:
- 13b+b+c=122
Step 7: Solve the equations
1. Substitute b=4c into the equation:
- 13(4c)+4c+c=122
- This simplifies to 43c+4c+c=122
- Combine like terms: 43c+123c=163c=122
- Solve for c: c=122×316=3352
Step 8: Calculate individual times
1. Now, using the efficiencies:
- For A: a=13b and b=4c
- For B: b=4c=4×3352=12352=388
- For C: c=3352
Step 9: Calculate the time taken by each
1. Time taken by A = 1a=1388=883≈29.33 days
2. Time taken by B = 1b=1388=88 days
3. Time taken by C = 1c=13352=352/3≈117.33 days
Final Answer:
- A will take approximately 29.33 days,
- B will take 88 days,
- C will take approximately 117.33 days.
1. Let the time taken by B and C together to complete the work be x days.
2. According to the problem, A takes three times as long as B and C together, so A takes 3x days.
3. The efficiency of A is 13x and the efficiency of B + C is 1x.
1. Let the time taken by A + C together be y days.
2. According to the problem, B takes four times as long as A + C together, so B takes 4y days.
3. The efficiency of B is 14y and the efficiency of A + C is 1y.
1. From the efficiencies, we have:
- Efficiency of A = 13x
- Efficiency of B + C = 1x
- Efficiency of B = 14y
- Efficiency of A + C = 1y
1. Since B + C = A + C + B, we can express the efficiencies:
- Efficiency of A + B + C = Efficiency of A + Efficiency of B + Efficiency of C
- From the given information, we know that A takes 3 times as long as B + C, and B takes 4 times as long as A + C.
1. We know that A + B + C working together can complete the work in 22 days, which means their combined efficiency is 122.
2. Therefore, Efficiency of A+Efficiency of B+Efficiency of C=122.
1. Let’s assume the efficiencies of A, B, and C are a,b,c respectively.
2. From the relationships, we can derive:
- a=13b
- b=14c
3. Substitute these into the equation for total efficiency:
- 13b+b+c=122
1. Substitute b=4c into the equation:
- 13(4c)+4c+c=122
- This simplifies to 43c+4c+c=122
- Combine like terms: 43c+123c=163c=122
- Solve for c: c=122×316=3352
1. Now, using the efficiencies:
- For A: a=13b and b=4c
- For B: b=4c=4×3352=12352=388
- For C: c=3352
1. Time taken by A = 1a=1388=883≈29.33 days
2. Time taken by B = 1b=1388=88 days
3. Time taken by C = 1c=13352=352/3≈117.33 days
- A will take approximately 29.33 days,
- B will take 88 days,
- C will take approximately 117.33 days.
Topper's Solved these Questions
Similar Questions
B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.
View SolutionB takes two times time as long as (A + C) together take to complete a work C takes three times time as much as (A + B) together take to complete a work. If all three working together can complete the work in 25 days. Then find the number of days in which A, B and C can complete the work individually.
View Solution
Knowledge Check
- Question 1 - Select One
A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is
A100B96C95D90 - Question 2 - Select One
A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30 - Question 3 - Select One
A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30
A takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA takes 6 hours more than (A + B + C) together to complete a work. B takes 1 hours more than (A + B + C) together to complete a work. C takes twice as (A + B + C) together to complete a work. In how many days will A and B together complete this work ?
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View SolutionA and B working together can do 30% of the work in 6 days. B alone can do the same work in 25 days. How long will A alone take to complete the same work?
View Solution