Doubtnut Promotions Sticky

A takes 9 days more than B to do a certain piece of work. Together they can do the work in 6 days. How many days will A alone take to do the work?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:18 days


To solve the problem, we need to find out how many days A alone will take to complete the work. Let's break down the solution step by step.

Step 1: Define Variables
Let:
- y = number of days B takes to complete the work.
- x = number of days A takes to complete the work.

From the problem, we know that:
x=y+9
(This means A takes 9 days more than B.)

Step 2: Set Up the Equation for Combined Work
When A and B work together, they can complete the work in 6 days. Therefore, their combined work rate can be expressed as:
1x+1y=16

Step 3: Substitute for x
Substituting x from Step 1 into the equation:
1y+9+1y=16

Step 4: Find a Common Denominator
To combine the fractions on the left-hand side, we need a common denominator:
y+y+9y(y+9)=16
This simplifies to:
2y+9y(y+9)=16

Step 5: Cross Multiply
Cross multiplying gives us:
6(2y+9)=y(y+9)

Step 6: Expand and Rearrange
Expanding both sides:
12y+54=y2+9y

Rearranging the equation:
y2+9y12y54=0
This simplifies to:
y23y54=0

Step 7: Factor the Quadratic Equation
We need to factor the quadratic equation:
(y9)(y+6)=0

Step 8: Solve for y
Setting each factor to zero gives:
1. y9=0y=9
2. y+6=0y=6 (not valid since days cannot be negative)

Thus, y=9.

Step 9: Find x
Now, substituting y back into the equation for x:
x=y+9=9+9=18

Conclusion
A alone will take 18 days to complete the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions