A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:120

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months? by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.

    A6 hours
    B(6)1/2 hours
    C7 hours
    D9 hours
  • 7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

    A28
    B21
    C14
    D7
  • 45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?

    A10
    B16
    C18
    D15