An employer has a workforce of 300 employees to finish a project in 8 months.How many extra employees should he employ to complete the project in 6 months?
Step by step video & image solution for An employer has a workforce of 300 employees to finish a project in 8 months.How many extra employees should he employ to complete the project in 6 months? by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.
Updated on:21/07/2023Similar Questions
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
View SolutionA work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
View Solution
Knowledge Check
21 typist can complete a task in 8 days. Then in how many days 15 typist can complete that task?
21 टाइपिस्ट 8 दिनों में एक कार्य पूरा कर सकता है। फिर 15 टाइपिस्ट कितने दिनों में उस कार्य को पूरा करेंगे ?A5.8B11.2C9.3D740 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
A100B60C75DNone of these
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
View SolutionSeventy-five men are employed to lay down a railway line in 3 months. Due to certain emergency conditions, the work was to be finished in 18 days. How many more men . should be employed to complete the work in the desired time?
View SolutionA work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
View SolutionA work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View Solution