Doubtnut Promotions Sticky

If 48 men can dig a trench 14 days.how long will 28 men take to dig a simillar trench ?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:24 days


To solve the problem step by step, we will use the concept of the Unitary Method.

Step 1: Understand the given information
We know that 48 men can dig a trench in 14 days.

Step 2: Calculate the total work done in man-days
First, we need to find out the total amount of work done in man-days.
- Total work = Number of men × Number of days
- Total work = 48 men × 14 days = 672 man-days

Step 3: Determine the work done by one man
Now, we can find out how much work one man can do in one day.
- Work done by one man in one day = Total work / Number of men
- Work done by one man in one day = 672 man-days / 48 men = 14 days

Step 4: Calculate how long it will take for 28 men to do the same work
Now, we need to find out how many days it will take for 28 men to complete the same amount of work (672 man-days).
- Number of days required = Total work / Number of men
- Number of days required = 672 man-days / 28 men = 24 days

Conclusion
Therefore, it will take 28 men 24 days to dig a similar trench.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 48 men can dig a trench in 14 days, how long will 42 men take to dig a similar trench?

    A16 days
    B17 days
    C18 days
    D19 days
  • Question 2 - Select One

    50 men can dig 40 holes in 30 days.How long will 25 men take to dig 20 holes?

    A15 days
    B2212 days
    C30 days
    D45 days
  • Question 3 - Select One

    50 men can dig 40 holes in 30 days. How long will 25 men take to dig 30 holes?

    A15 days
    B221/2 days
    C30 days
    D45 days