If 8 men or 12 women can do a piece of work in 10 days, then what is the number of days required by 4 men and 4 women to finish the work ?

A

12 days

B

22 days

C

10 days

D

None of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:12 days.


To solve the problem step by step, we can follow these instructions:

Step 1: Determine the total work done by men and women
We know that:
- 8 men can complete the work in 10 days.
- 12 women can complete the work in 10 days.

First, we calculate the total work in terms of "man-days" and "woman-days."

Total work in man-days:
Total work=Number of men×Number of days=8 men×10 days=80 man-days

Total work in woman-days:
Total work=Number of women×Number of days=12 women×10 days=120 woman-days

Step 2: Calculate the work done by one man and one woman in one day
Now we find out how much work one man and one woman can do in one day.

Work done by one man in one day:
Work done by 1 man in 1 day=180 of the work

Work done by one woman in one day:
Work done by 1 woman in 1 day=1120 of the work

Step 3: Calculate the work done by 4 men and 4 women in one day
Now, we calculate the combined work done by 4 men and 4 women in one day.

Work done by 4 men in one day:
Work done by 4 men in 1 day=4×180=480=120

Work done by 4 women in one day:
Work done by 4 women in 1 day=4×1120=4120=130

Step 4: Combine the work done by 4 men and 4 women
Now we add the work done by 4 men and 4 women in one day:
Total work done by 4 men and 4 women in 1 day=120+130

Step 5: Find the LCM and add the fractions
To add these fractions, we need to find the least common multiple (LCM) of 20 and 30, which is 60.

Convert the fractions:
120=360(since 20×3=60)
130=260(since 30×2=60)

Add the fractions:
360+260=560=112

Step 6: Calculate the total days required to finish the work
If 4 men and 4 women together do 112 of the work in one day, then the total number of days required to finish the work is the reciprocal of 112:
Total days required=1112=12 days

Final Answer:
The number of days required by 4 men and 4 women to finish the work is 12 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 5 men or 8 women can do a piece of work in 12 days, how many days will be taken by 2 men and 4 women to do the same work?

    A15 days
    B13 days
    C13 +1/3days
    D10 days
  • Where 6 men and 9 women can complete a piece of work in 10 days, What is the time taken by 4 men and 6 women to complete it ?

    A10 days
    B12 days
    C15 days
    D18 days
  • 2 men or 5 women or 7 boys can finish a work in 469 days. then the number of days taken by 7 men, 5 women and 2 boys to finish the work is :

    A134
    B106
    C100
    D98