Doubtnut Promotions Sticky

If 16 men or 20 women can do a piece of work in 25 days, in what time will 28 men and 15 women do it ?

A

1427 days

B

3313 days

C

1834 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step-by-step, we will follow these calculations:

Step 1: Determine the total work done by men and women in days.
We know that:
- 16 men can complete the work in 25 days.
- 20 women can complete the work in 25 days.

Step 2: Calculate the total work in man-days.
The total work can be calculated in terms of man-days:
- Work done by 16 men in 25 days = 16 men × 25 days = 400 man-days.

Step 3: Calculate the total work in woman-days.
Similarly, for women:
- Work done by 20 women in 25 days = 20 women × 25 days = 500 woman-days.

Step 4: Find the work done by one man and one woman in one day.
Now, let's find the work done by one man in one day:
- Since 16 men complete the work in 25 days, one man will take 400 days to complete the work alone. Thus, the work done by one man in one day = 1/400 of the work.

Now, for one woman:
- Since 20 women complete the work in 25 days, one woman will take 500 days to complete the work alone. Thus, the work done by one woman in one day = 1/500 of the work.

Step 5: Calculate the work done by 28 men in one day.
Now we calculate the work done by 28 men in one day:
- Work done by 28 men in one day = 28 × (1/400) = 28/400 = 7/100 of the work.

Step 6: Calculate the work done by 15 women in one day.
Now we calculate the work done by 15 women in one day:
- Work done by 15 women in one day = 15 × (1/500) = 15/500 = 3/100 of the work.

Step 7: Combine the work done by men and women.
Now, we add the work done by 28 men and 15 women in one day:
- Total work done in one day = (7/100) + (3/100) = (7 + 3)/100 = 10/100 = 1/10 of the work.

Step 8: Calculate the total time taken to complete the work.
If 28 men and 15 women together can complete 1/10 of the work in one day, then to complete the entire work:
- Time taken = 1 / (1/10) = 10 days.

Final Answer:
Thus, 28 men and 15 women will complete the work in 10 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 12 men or 18 women can do a piece of work in 14 days, then how long will 8 men and 16 women take to finish the work ?

    A9 days
    B10 days
    C12 days
    D14 days
  • Question 2 - Select One

    If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

    A4 days
    B5 days
    C3 days
    D2 days
  • Question 3 - Select One

    If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

    A4 days
    B5 days
    C3 days
    D2 days