Doubtnut Promotions Sticky

If six men can do a piece of work in 6 days, then 3 men can do same work in
(a) 10 days       
(b)   12 days        
(c)   15 days  
(d)  18 days

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will use the concept of work done, which is calculated using the formula:

Work Done = Number of Men × Number of Days

1. Identify the Work Done by Six Men:
We know that six men can complete the work in 6 days.
Work Done=6 men×6 days=36 man-days

2. Set Up the Equation for Three Men:
Now, we need to find out how many days (let's call it x) three men will take to complete the same work. The work done remains the same, which is 36 man-days.
Work Done=3 men×x days=36 man-days

3. Create the Equation:
From the above, we can set up the equation:
3x=36

4. Solve for x:
To find x, divide both sides of the equation by 3:
x=363=12

5. Conclusion:
Therefore, three men can complete the same work in 12 days.

Answer:
(b) 12 days

---

|