P and Q can do a piece of work in 10 days, Q and R can do same work in 15 days, R and P can do the same work in 20 days. Then in how many days R will complete it alone.
115 days
110 days
130 days
120 days
The correct Answer is:D
To solve the problem step by step, we will first determine the efficiencies of P, Q, and R based on the information given about their combined work rates.
Step 1: Determine the total work
Let the total work be represented by the least common multiple (LCM) of the days taken by the pairs to complete the work. The pairs are:
- P and Q can do the work in 10 days.
- Q and R can do the work in 15 days.
- R and P can do the work in 20 days.
To find the LCM of 10, 15, and 20:
- The prime factorization of 10 is 2×5.
- The prime factorization of 15 is 3×5.
- The prime factorization of 20 is 22×5.
The LCM is calculated by taking the highest power of each prime:
- For 2: 22
- For 3: 31
- For 5: 51
Thus, LCM=22×31×51=4×3×5=60.
Step 2: Calculate efficiencies
Now we can calculate the efficiencies of each pair:
- Efficiency of P and Q = Total work / Time = 60/10=6 units/day.
- Efficiency of Q and R = Total work / Time = 60/15=4 units/day.
- Efficiency of R and P = Total work / Time = 60/20=3 units/day.
Let:
- Efficiency of P = P
- Efficiency of Q = Q
- Efficiency of R = R
From the above, we can set up the following equations:
1. P+Q=6 (Equation 1)
2. Q+R=4 (Equation 2)
3. R+P=3 (Equation 3)
Step 3: Solve the equations
Now we will add all three equations together:
(P+Q)+(Q+R)+(R+P)=6+4+3
This simplifies to:
2P+2Q+2R=13
Dividing by 2:
P+Q+R=132=6.5(Equation4)
Step 4: Find individual efficiencies
Now we can find the individual efficiencies:
- From Equation 1: Q=6−P
- Substitute Q in Equation 2:
(6−P)+R=4⟹R=4−(6−P)=P−2
- Substitute R in Equation 3:
(P−2)+P=3⟹2P−2=3⟹2P=5⟹P=2.5
- Now substitute P back to find Q and R:
Q=6−2.5=3.5
R=P−2=2.5−2=0.5
Step 5: Calculate the time taken by R to complete the work alone
To find the time taken by R to complete the work alone, we use the formula:
Time=Total WorkEfficiency of R=600.5=120 days
Final Answer
R will complete the work alone in 120 days.
---
Let the total work be represented by the least common multiple (LCM) of the days taken by the pairs to complete the work. The pairs are:
- P and Q can do the work in 10 days.
- Q and R can do the work in 15 days.
- R and P can do the work in 20 days.
- The prime factorization of 10 is 2×5.
- The prime factorization of 15 is 3×5.
- The prime factorization of 20 is 22×5.
- For 2: 22
- For 3: 31
- For 5: 51
Now we can calculate the efficiencies of each pair:
- Efficiency of P and Q = Total work / Time = 60/10=6 units/day.
- Efficiency of Q and R = Total work / Time = 60/15=4 units/day.
- Efficiency of R and P = Total work / Time = 60/20=3 units/day.
- Efficiency of P = P
- Efficiency of Q = Q
- Efficiency of R = R
1. P+Q=6 (Equation 1)
2. Q+R=4 (Equation 2)
3. R+P=3 (Equation 3)
Now we will add all three equations together:
(P+Q)+(Q+R)+(R+P)=6+4+3
This simplifies to:
2P+2Q+2R=13
Dividing by 2:
P+Q+R=132=6.5(Equation4)
Now we can find the individual efficiencies:
- From Equation 1: Q=6−P
- Substitute Q in Equation 2:
(6−P)+R=4⟹R=4−(6−P)=P−2
- Substitute R in Equation 3:
(P−2)+P=3⟹2P−2=3⟹2P=5⟹P=2.5
- Now substitute P back to find Q and R:
Q=6−2.5=3.5
R=P−2=2.5−2=0.5
To find the time taken by R to complete the work alone, we use the formula:
Time=Total WorkEfficiency of R=600.5=120 days
R will complete the work alone in 120 days.
Topper's Solved these Questions
- MAT STAGE 2 (2019-20)BOOK - OSWAL PUBLICATIONCHAPTER - MAT STAGE 2 (2019-20)EXERCISE - M.C.Q
97 Videos
- NEW TYPOLOGIES INTRODUCED BY CBSE FOR BOARD 2021-22 EXAM BOOK - OSWAL PUBLICATIONCHAPTER - NEW TYPOLOGIES INTRODUCED BY CBSE FOR BOARD 2021-22 EXAM EXERCISE - UNIT-VII STATISTICS AND PROBABILITY (STATISTICS) (SELF ASSESSMENT)
2 Videos
Similar Questions
P and Q can do a piece of work in 24 days. Q and R can do same piece of work in 30 days and R and P can do it in 40 days. In how many days will they finish it together and separately?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View Solution
Knowledge Check
A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?
A120 daysB118 daysC115 daysD110 daysP and Q can do a piece of work in 8 days, Q and R can do the same work in 12 days and P and R complete it in 8 days In how many days can P,Q and R complete the whole work, working together?
A4B6C12D9A and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :
A1313 daysB12 daysC16 daysD11 days
A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View Solution(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View SolutionIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 men
View SolutionA and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
View Solution