P and Q can do a piece of work in 10 days, Q and R can do same work in 15 days, R and P can do the same work in 20 days. Then in how many days R will complete it alone.

A

115 days

B

110 days

C

130 days

D

120 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the efficiencies of P, Q, and R based on the information given about their combined work rates.

Step 1: Determine the total work
Let the total work be represented by the least common multiple (LCM) of the days taken by the pairs to complete the work. The pairs are:
- P and Q can do the work in 10 days.
- Q and R can do the work in 15 days.
- R and P can do the work in 20 days.

To find the LCM of 10, 15, and 20:
- The prime factorization of 10 is 2×5.
- The prime factorization of 15 is 3×5.
- The prime factorization of 20 is 22×5.

The LCM is calculated by taking the highest power of each prime:
- For 2: 22
- For 3: 31
- For 5: 51

Thus, LCM=22×31×51=4×3×5=60.

Step 2: Calculate efficiencies
Now we can calculate the efficiencies of each pair:
- Efficiency of P and Q = Total work / Time = 60/10=6 units/day.
- Efficiency of Q and R = Total work / Time = 60/15=4 units/day.
- Efficiency of R and P = Total work / Time = 60/20=3 units/day.

Let:
- Efficiency of P = P
- Efficiency of Q = Q
- Efficiency of R = R

From the above, we can set up the following equations:
1. P+Q=6 (Equation 1)
2. Q+R=4 (Equation 2)
3. R+P=3 (Equation 3)

Step 3: Solve the equations
Now we will add all three equations together:
(P+Q)+(Q+R)+(R+P)=6+4+3
This simplifies to:
2P+2Q+2R=13
Dividing by 2:
P+Q+R=132=6.5(Equation4)

Step 4: Find individual efficiencies
Now we can find the individual efficiencies:
- From Equation 1: Q=6P
- Substitute Q in Equation 2:
(6P)+R=4R=4(6P)=P2
- Substitute R in Equation 3:
(P2)+P=32P2=32P=5P=2.5
- Now substitute P back to find Q and R:
Q=62.5=3.5
R=P2=2.52=0.5

Step 5: Calculate the time taken by R to complete the work alone
To find the time taken by R to complete the work alone, we use the formula:
Time=Total WorkEfficiency of R=600.5=120 days

Final Answer
R will complete the work alone in 120 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?

    A120 days
    B118 days
    C115 days
    D110 days
  • P and Q can do a piece of work in 8 days, Q and R can do the same work in 12 days and P and R complete it in 8 days In how many days can P,Q and R complete the whole work, working together?

    A4
    B6
    C12
    D9
  • A and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :

    A1313 days
    B12 days
    C16 days
    D11 days