If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
The correct Answer is:2211days
To solve the problem, we need to find out how long A, B, and C will take to complete the work when they work together. We can do this by calculating their individual work rates and then combining them.
1. Determine the Work Rates:
- A can complete the work in 4 days, so A's work rate is 14 of the work per day.
- B can complete the work in 8 days, so B's work rate is 18 of the work per day.
- C can complete the work in 12 days, so C's work rate is 112 of the work per day.
2. Combine the Work Rates:
- To find the combined work rate of A, B, and C, we add their individual work rates:
Combined Work Rate=14+18+112
3. Find a Common Denominator:
- The least common multiple (LCM) of 4, 8, and 12 is 24. We will convert each fraction to have a denominator of 24:
14=624,18=324,112=224
4. Add the Fractions:
- Now we can add the fractions:
624+324+224=6+3+224=1124
5. Calculate the Time Taken to Complete the Work:
- The combined work rate of A, B, and C is 1124 of the work per day. To find the total time taken to complete the work, we take the reciprocal of the combined work rate:
Time=11124=2411 days
6. Final Answer:
- Thus, working together, A, B, and C will take 2411 days to complete the work, which is approximately 2.18 days.
- A can complete the work in 4 days, so A's work rate is 14 of the work per day.
- B can complete the work in 8 days, so B's work rate is 18 of the work per day.
- C can complete the work in 12 days, so C's work rate is 112 of the work per day.
- To find the combined work rate of A, B, and C, we add their individual work rates:
Combined Work Rate=14+18+112
- The least common multiple (LCM) of 4, 8, and 12 is 24. We will convert each fraction to have a denominator of 24:
14=624,18=324,112=224
- Now we can add the fractions:
624+324+224=6+3+224=1124
- The combined work rate of A, B, and C is 1124 of the work per day. To find the total time taken to complete the work, we take the reciprocal of the combined work rate:
Time=11124=2411 days
- Thus, working together, A, B, and C will take 2411 days to complete the work, which is approximately 2.18 days.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE BASE LEVEL QUESTION68videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
- BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)7videos
WORK AND WAGES
Similar Questions
A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
View SolutionIf A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
A819B989C889D918 - Question 2 - Select One
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
A8B10C12D16 - Question 3 - Select One
A can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
A24 daysB18 daysC20 daysD16 days
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and B can do a certain work in 12 days, B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work ?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and B can do a certain work in 12 days. B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work?
View SolutionIf P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?View Solution