Doubtnut Promotions Sticky

Pintu takes 6 days more than those of Nishu to complete certain work. If they work togeter they finish it in 4 days. How many days would it take to complete the work if they work alone.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:Nishu takes 6 days and Pintu takes 12 days to complete the work individually.


Let Nishu take x days to complete the work. Then Pintu takes (x+6) days to complete the same work.
In one day, Nishu does 1x part of the work and Pintu does 1x+6 part of the work.
in 1 day they together do (1x+1x+6) part of the work
1x+1x+6=x+6+xx(x+6)=2x+6x2+6x
total number of days taken by them together to complete the work is x2+6x2x+6
From the given condition,
x2+6x2x+6=4 x2+6x=4(2x+6)
x2+6x=8x+24 x2+6x8x24=0
x22x24=0 x26x+4x24=0
x(x6)+4(x6)=0 (x6)(x+4)=0
x6=0orx+4=0 x=6orx=4
But the number of days cannot be negative.
x=4 is unacceptable.
x=6 x+6=6+6=12

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?

    A27
    B24
    C36
    D42
  • Question 2 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days
  • Question 3 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days