Pintu takes 6 days more than those of Nishu to complete certain work. If they work togeter they finish it in 4 days. How many days would it take to complete the work if they work alone.
The correct Answer is:Nishu takes 6 days and Pintu takes 12 days to complete the work individually.
Let Nishu take x days to complete the work. Then Pintu takes (x+6) days to complete the same work.
In one day, Nishu does 1x part of the work and Pintu does 1x+6 part of the work.
∴ in 1 day they together do (1x+1x+6) part of the work
1x+1x+6=x+6+xx(x+6)=2x+6x2+6x
∴ total number of days taken by them together to complete the work is x2+6x2x+6
From the given condition,
x2+6x2x+6=4 ∴x2+6x=4(2x+6)
∴x2+6x=8x+24 ∴x2+6x−8x−24=0
∴x2−2x−24=0 ∴x2−6x+4x−24=0
∴x(x−6)+4(x−6)=0 ∴(x−6)(x+4)=0
∴x−6=0orx+4=0 ∴x=6orx=−4
But the number of days cannot be negative.
∴x=−4 is unacceptable.
∴x=6 x+6=6+6=12
Topper's Solved these Questions
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUADRATIC EQUATION EXERCISE - PROBLEM SET -21videos
QUADRATIC EQUATION
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUADRATIC EQUATION EXERCISE - PROBLEM SET -31videos
QUADRATIC EQUATION
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUADRATIC EQUATION EXERCISE - PRACTICE SET 2.514videos
QUADRATIC EQUATION
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - PYTHAGORAS THEOREMEXERCISE - Challenging Questions5videos
PYTHAGORAS THEOREM
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUADRATIC EQUATIONS EXERCISE - ASSIGNEMENT 2.48videos
QUADRATIC EQUATIONS
Similar Questions
Knowledge Check
- Question 1 - Select One
A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42 - Question 2 - Select One
A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) days - Question 3 - Select One
A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) days
Acan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
View SolutionA alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionA can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?
View Solution