Doubtnut Promotions Sticky

A can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?

A

8

B

3

C

4

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's define the variables and equations based on the information given in the question.

Step 1: Define the variables
Let A take x days to complete the work. Therefore, B takes x+3 days to complete the same work.

Step 2: Determine the work done per day
The work done by A in one day is 1x (since A completes the work in x days), and the work done by B in one day is 1x+3.

Step 3: Set up the equation for combined work
When A and B work together, they complete the work in 2 days. Therefore, their combined work done in one day is 12.

So, we can write the equation:
1x+1x+3=12

Step 4: Find a common denominator
To solve the equation, we need to find a common denominator for the left side. The common denominator is x(x+3):
x+3+xx(x+3)=12
This simplifies to:
2x+3x(x+3)=12

Step 5: Cross-multiply to eliminate the fraction
Cross-multiplying gives us:
2(2x+3)=x(x+3)
Expanding both sides results in:
4x+6=x2+3x

Step 6: Rearrange the equation
Rearranging the equation to one side gives:
x2+3x4x6=0
This simplifies to:
x2x6=0

Step 7: Factor the quadratic equation
Now, we can factor the quadratic equation:
(x3)(x+2)=0
Setting each factor to zero gives us:
x3=0orx+2=0
Thus, x=3 or x=2.

Step 8: Determine the valid solution
Since x represents the number of days A takes to complete the work, it must be a positive number. Therefore, we take x=3.

Step 9: Calculate the days B takes
Now, we can find the number of days B takes:
x+3=3+3=6

Final Answer
B takes 6 days to complete the work.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A work three times as fast as B.B takes 56 days more than A to complete a work. Working together in how days can they complete the work?

    A24
    B21
    C27
    D29
  • Question 2 - Select One

    A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

    A4813 days
    B3513 days
    C267 days
    D247 days
  • Question 3 - Select One

    A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

    A6 days
    B4 days
    C10 days
    D8 days