Doubtnut Promotions Sticky

Pintu takes 6 days more than those of Nishu to complete certain work. If they work togeter they finish it in 4 days. How many days would it take to complete the work if they work alone.

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:6 days and 12 days respectively.


To solve the problem step by step, we can follow these instructions:

Step 1: Define Variables
Let x be the number of days Nishu takes to complete the work. According to the problem, Pintu takes 6 days more than Nishu, so he takes x+6 days.

Step 2: Set Up the Work Equation
When they work together, they complete the work in 4 days. Therefore, the work done by both Nishu and Pintu in one day can be expressed as:
1x+1x+6=14

Step 3: Clear the Denominators
To eliminate the fractions, we can multiply through by 4x(x+6):
4(x+6)+4x=x(x+6)

Step 4: Expand and Rearrange
Expanding both sides gives:
4x+24+4x=x2+6x
Combining like terms results in:
8x+24=x2+6x
Rearranging the equation leads to:
x22x24=0

Step 5: Factor the Quadratic Equation
Now we need to factor the quadratic equation x22x24=0. We look for two numbers that multiply to 24 and add to 2. The numbers are 6 and 4:
(x6)(x+4)=0

Step 6: Solve for x
Setting each factor to zero gives us:
1. x6=0x=6
2. x+4=0x=4 (not possible since days cannot be negative)

Thus, x=6.

Step 7: Calculate Days for Pintu
Since Nishu takes x=6 days, Pintu takes:
x+6=6+6=12 days

Conclusion
Nishu would take 6 days to complete the work alone, and Pintu would take 12 days to complete the work alone.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?

    A27
    B24
    C36
    D42
  • Question 2 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days
  • Question 3 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days