Pintu takes 6 days more than those of Nishu to complete certain work. If they work together, they finish it in 4 days. How many days would it take to complete the work if they work alone?Solution in Tamil
The correct Answer is:Nishu takes 6 days and pintu takes 12 days to complete the work .
Step by step video, text & image solution for Pintu takes 6 days more than those of Nishu to complete certain work. If they work together, they finish it in 4 days. How many days would it take to complete the work if they work alone? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Topper's Solved these Questions
- BOOK - CHETAN PUBLICATIONCHAPTER - QUADRATIC EQUATIONSEXERCISE - PROBLEM SET 250videos
QUADRATIC EQUATIONS
- BOOK - CHETAN PUBLICATIONCHAPTER - QUADRATIC EQUATIONSEXERCISE - PROBLEMS FOR PRACTICE21videos
QUADRATIC EQUATIONS
- BOOK - CHETAN PUBLICATIONCHAPTER - QUADRATIC EQUATIONSEXERCISE - PRACTICE SET 2.515videos
QUADRATIC EQUATIONS
- BOOK - CHETAN PUBLICATIONCHAPTER - PYTHAGORAS THEOREMEXERCISE - ASSIGNMENT -51videos
PYTHAGORAS THEOREM
- BOOK - CHETAN PUBLICATIONCHAPTER - SIMILARITY EXERCISE - ASSIGNMENT-112videos
SIMILARITY
Similar Questions
Which of the following are quadratic equations?
x2+2x+11=002:47View SolutionIf x=9 is one root of the quadratic equation x2−11x+k=0, then find the value of k.
05:37View SolutionFind the value of discriminant.
x2+7x−1=004:24View SolutionSolve the following sub question :
In an equilateral triangle ABC, the side BC is trisected at D. prove that 9AD2=7AB203:31View SolutionSelect the appropriate alternative : In the adjoining figure ,PQ∣∣AC.BP=6,PA=8,BQ=9 , then QC = ……………
03:00View SolutionFor doing some work, Pintu takes 6 days more than Nishu. If both work together, they complete the work in 4 days. Find the number of days if Pintu and Nishu work alone.
11:22View SolutionPintu takes 6 days more than those of Nishu to complete certain work. If they work togeter they finish it in 4 days. How many days would it take to complete the work if they work alone.
03:39View SolutionA' takes 6 days less than 'B' to complete a piece of work. If both work together they can complete the same work in 4 days. In how many days will 'B' alone complete the work?
01:25View SolutionPintu takes 6 days more than Nishu to complete certain work. If they work together, they finish it in 4 days. How many days would it take to complete the work if they work alone?
01:58View SolutionFor doing some work, Pintu takes 6 days more than Nishu. If both work together, then they complete the work in 4 days. Find the number of days taken, if Pintu and Nishu work alone.
02:07View SolutionPintu takes 6 days more than those of Nishu to complete certain
work. If they work togeter they finish it in 4 days. How many days would it take to complete the work if they work alone.02:45View SolutionShweta takes 6 days less , than the Ankitha to complete the work. The same work is completed together in 4 days. How many days required to complete the work by Ankitha alone?
06:34View SolutionA takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
01:56View SolutionA takes 412 days more than (A + B) together to complete a work. B takes 8 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
03:48View SolutionA takes 7 days more than B and 16 days more than C to complete a work. C works as much as (A + B) works together. In how many days will A, B and C alone complete this work ?
04:31View Solution