A takes 7 days more than B and 16 days more than C to complete a work. C works as much as (A + B) works together. In how many days will A, B and C alone complete this work ?
The correct Answer is:A → 28 days, B → 21 days, C → 12 days
To solve the problem step by step, let's denote the number of days taken by each person to complete the work as follows:
- Let C take x days to complete the work.
- Then, A takes x+16 days to complete the work.
- B takes x+7 days to complete the work.
From the problem, we also know that C works as much as A and B together. This means that the work done by C in one day is equal to the combined work done by A and B in one day.
Step 1: Establish the relationship between their work rates
The work done in one day by each person can be expressed as:
- Work rate of A = 1x+16
- Work rate of B = 1x+7
- Work rate of C = 1x
According to the problem:
1x=1x+16+1x+7
Step 2: Solve the equation
To solve the equation, we can find a common denominator and simplify:
1x=(x+7)+(x+16)(x+16)(x+7)
This simplifies to:
1x=2x+23(x+16)(x+7)
Cross-multiplying gives us:
(x+16)(x+7)=x(2x+23)
Step 3: Expand both sides
Expanding both sides:
x2+23x+112=2x2+23x
Step 4: Rearranging the equation
Rearranging the equation gives:
x2+112=0
This leads to:
x2=112
Step 5: Finding the value of x
Taking the square root:
x=√112=4√7
Step 6: Calculate A and B's days
Now, substituting x back to find A and B's days:
- C's days = x=4√7
- A's days = x+16=4√7+16
- B's days = x+7=4√7+7
Final Answer
Thus, the number of days taken by A, B, and C to complete the work alone are:
- A: 4√7+16 days
- B: 4√7+7 days
- C: 4√7 days
- Then, A takes x+16 days to complete the work.
- B takes x+7 days to complete the work.
The work done in one day by each person can be expressed as:
- Work rate of A = 1x+16
- Work rate of B = 1x+7
- Work rate of C = 1x
1x=1x+16+1x+7
To solve the equation, we can find a common denominator and simplify:
1x=(x+7)+(x+16)(x+16)(x+7)
This simplifies to:
1x=2x+23(x+16)(x+7)
(x+16)(x+7)=x(2x+23)
Expanding both sides:
x2+23x+112=2x2+23x
Rearranging the equation gives:
x2+112=0
This leads to:
x2=112
Taking the square root:
x=√112=4√7
Now, substituting x back to find A and B's days:
- C's days = x=4√7
- A's days = x+16=4√7+16
- B's days = x+7=4√7+7
Thus, the number of days taken by A, B, and C to complete the work alone are:
- A: 4√7+16 days
- B: 4√7+7 days
- C: 4√7 days
Topper's Solved these Questions
Similar Questions
A takes 24 days more than B and 32 days more than C to complete a work. C works as much as (A + B) works together. In how many days will A, B and C alone complete this work ?
View SolutionA takes 5 days more than B and 9 days more than C to complete a work. C works as much as (A + B) works together. In how many days will B and C together complete this work ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 2 - Select One
A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
A40B36C45D32 - Question 3 - Select One
A can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?
A8B3C4D6
A takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA takes 513 days more than (A + B) together to complete a work. B takes 813 days more than (A + B) together to complete a work. In how many days will A and B alone complete this work ?
View SolutionA takes 412 days more than (A + B) together to complete a work. B takes 8 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA takes 6 hours more than (A + B + C) together to complete a work. B takes 1 hours more than (A + B + C) together to complete a work. C takes twice as (A + B + C) together to complete a work. In how many days will A and B together complete this work ?
View SolutionB works four times as much as A. If B takes 15 days less than A to complete this work. In how many days will A and B alone complete this work ?
View Solution