Pooja and Ritu can do a piece of work in 17.17 days. If one day work of Pooja be three fourth of one day work of Ritu. Find in how many days each will do the work alone.
The correct Answer is:x=40 days , y=30 days
To solve the problem step by step, we will follow the reasoning provided in the video transcript:
Step 1: Understand the problem
Pooja and Ritu can complete a piece of work together in 1717 days. We need to find out how many days each of them will take to complete the work alone.
Step 2: Convert mixed fraction to improper fraction
First, we convert 1717 into an improper fraction:
1717=17×7+17=119+17=1207 days
Step 3: Define variables for individual work
Let:
- X = number of days Pooja takes to complete the work alone
- Y = number of days Ritu takes to complete the work alone
Step 4: Write the equations based on work done
Since they can complete the work together in 1207 days, their combined work done in one day is:
Work done in 1 day=11207=7120
Step 5: Express individual work rates
The work done by Pooja in one day is 1X and by Ritu in one day is 1Y. Thus, we can write:
1X+1Y=7120
Step 6: Use the relationship between their work rates
According to the problem, Pooja's one day work is 34 of Ritu's one day work:
1X=34⋅1Y
From this, we can express 1X in terms of Y:
1X=34Y
Step 7: Substitute into the combined work equation
Substituting 1X into the combined work equation:
34Y+1Y=7120
Combining the left side:
3+44Y=74Y=7120
Step 8: Cross-multiply to solve for Y
Cross-multiplying gives:
7⋅120=7⋅4Y
Cancelling 7 from both sides:
120=4Y
Dividing both sides by 4:
Y=30 days
Step 9: Find X
Now, substitute Y back to find X:
1X=34Y=34⋅30=3120=140
Thus,
X=40 days
Conclusion
Pooja takes 40 days to complete the work alone, and Ritu takes 30 days to complete the work alone.
Pooja and Ritu can complete a piece of work together in 1717 days. We need to find out how many days each of them will take to complete the work alone.
First, we convert 1717 into an improper fraction:
1717=17×7+17=119+17=1207 days
Let:
- X = number of days Pooja takes to complete the work alone
- Y = number of days Ritu takes to complete the work alone
Since they can complete the work together in 1207 days, their combined work done in one day is:
Work done in 1 day=11207=7120
The work done by Pooja in one day is 1X and by Ritu in one day is 1Y. Thus, we can write:
1X+1Y=7120
According to the problem, Pooja's one day work is 34 of Ritu's one day work:
1X=34⋅1Y
From this, we can express 1X in terms of Y:
1X=34Y
Substituting 1X into the combined work equation:
34Y+1Y=7120
Combining the left side:
3+44Y=74Y=7120
Cross-multiplying gives:
7⋅120=7⋅4Y
Cancelling 7 from both sides:
120=4Y
Dividing both sides by 4:
Y=30 days
Now, substitute Y back to find X:
1X=34Y=34⋅30=3120=140
Thus,
X=40 days
Pooja takes 40 days to complete the work alone, and Ritu takes 30 days to complete the work alone.
Topper's Solved these Questions
- SIMULTANEOUS LINEAR EQUATIONS IN TWO VARIABLESBOOK - ICSECHAPTER - SIMULTANEOUS LINEAR EQUATIONS IN TWO VARIABLESEXERCISE - Topic 2 (4 Marks questions)
8 Videos
- SIMULTANEOUS LINEAR EQUATIONS IN TWO VARIABLESBOOK - ICSECHAPTER - SIMULTANEOUS LINEAR EQUATIONS IN TWO VARIABLESEXERCISE - Topic 1 (4 Marks questions)
8 Videos
- SIMULTANEOUS EQUATIONSBOOK - ICSECHAPTER - SIMULTANEOUS EQUATIONSEXERCISE - EXERCISE 6 (G)
13 Videos
- SOLIDSBOOK - ICSECHAPTER - SOLIDSEXERCISE - Exercise 21(C )
10 Videos
Similar Questions
Pooja and Ritu can do a piece of work in 174 days. If one day work of Pooja be three fourth of one day work of Ritu, find in how many days each will do the work alone.
View SolutionA and B together can do a piece of work in 15 days. If one day's work of A be 112 times one day's work of B, find how many days will each take to finish the work alone?
View Solution72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?
View SolutionIf 78 men can do a work in 140 days, in how many days will 42 men do the same work ?
View SolutionA can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?
View SolutionIf 52 men can do a piece of work in 35 days in how many days 28 men will do it ?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionA can do a piece of work in 80 days and B in 100 days. They work together for first 20 days before B goes away. In how many days will A manage to finish the remaining work?
View SolutionA and B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
View Solution36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?
View Solution