Doubtnut Promotions Sticky

P,Q and R can complete a job in 6 days, 9 days and 12 days, respectively. They worked together and completed it. They earned a total of Rs. 2600. Find P's share ( in Rs.)

A

1350

B

1500

C

9000

D

1200

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D


Let the time taken to complete the job be x days.
Parts of the job complete by P,Q and R each day are 1 6 - 1 9 and 1 12 respectively
Parts of the job completd by P,Q and R are x ( 1 6 ) , x ( 1 9 ) and x ( 1 12 ) respectively.
Ratio of the parts of the job completed by P,Q and R = x 6 : x 9 : x 12 = 1 6 : 1 9 : 1 12 = 6 : 4 : 3
Ratio of the shares of P,Q and R = 6 : 4 : 3
P's share = 6 6 + 4 + 3 ( R s .2600 )
R s . 1200

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    X,Y and Z can complete a job in 24 days, 32 days and 48 days respectively. They worked together and earned a total of ₹ x.Find the ratio of their shares.

    A4:3:2
    B3:2:1
    C5:4:3
    D6:5:4
  • Question 2 - Select One

    P and Q can complete a job in 6 days and 7 days respectively. They worked together and earned a total of ₹ 780. Find P's share in this amount (in₹ ).

    A350
    B490
    C420
    D560
  • Question 3 - Select One

    P and Q can complete a job in 6 days and 7 days respectively. They worked together and earned a total of ₹ 780. Find P's share in this amount (in₹ ).

    A350
    B490
    C420
    D560