Doubtnut Promotions Sticky

Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?

A

18

B

10

C

16

D

8

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will use the information given in the question and apply the concept of work done, which is based on the number of workers, hours worked, and the total work.

Step 1: Calculate the total work done by 16 men in 15 days.
- Given: 16 men work for 6 hours a day for 15 days.
- Work done by 1 man in 1 hour: Let’s denote the work done by 1 man in 1 hour as x.
- Work done by 16 men in 1 hour: 16×x=16x.
- Work done by 16 men in 6 hours (1 day):
6 hours×16x=96x
- Work done by 16 men in 15 days:
15 days×96x=1440x
Thus, the total work W is 1440x.

Step 2: Calculate the work done by 18 men in 1 day.
- Given: 18 men working for 10 hours a day.
- Work done by 18 men in 1 hour:
18×x=18x
- Work done by 18 men in 10 hours (1 day):
10 hours×18x=180x

Step 3: Set up the equation to find the number of days T needed for 18 men to complete the work.
- Work done by 18 men in T days:
T×180x
- Since this work must equal the total work W:
T×180x=1440x

Step 4: Solve for T.
- Cancel x from both sides:
T×180=1440
- Divide both sides by 180:
T=1440180
- Simplifying the fraction:
T=8

Conclusion:
Therefore, 18 men working at 10 hours a day can complete the work in 8 days.

---

|
Updated on:18/9/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Twelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?

    A12
    B16
    C20
    D30
  • Question 2 - Select One

    Twelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?

    A12
    B16
    C20
    D30
  • Question 3 - Select One

    If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15521 days
    B1123 days
    C6916 days
    D415 days