Sixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
18
10
16
8
The correct Answer is:D
To solve the problem step by step, we will use the information given in the question and apply the concept of work done, which is based on the number of workers, hours worked, and the total work.
Step 1: Calculate the total work done by 16 men in 15 days.
- Given: 16 men work for 6 hours a day for 15 days.
- Work done by 1 man in 1 hour: Let’s denote the work done by 1 man in 1 hour as x.
- Work done by 16 men in 1 hour: 16×x=16x.
- Work done by 16 men in 6 hours (1 day):
6 hours×16x=96x
- Work done by 16 men in 15 days:
15 days×96x=1440x
Thus, the total work W is 1440x.
Step 2: Calculate the work done by 18 men in 1 day.
- Given: 18 men working for 10 hours a day.
- Work done by 18 men in 1 hour:
18×x=18x
- Work done by 18 men in 10 hours (1 day):
10 hours×18x=180x
Step 3: Set up the equation to find the number of days T needed for 18 men to complete the work.
- Work done by 18 men in T days:
T×180x
- Since this work must equal the total work W:
T×180x=1440x
Step 4: Solve for T.
- Cancel x from both sides:
T×180=1440
- Divide both sides by 180:
T=1440180
- Simplifying the fraction:
T=8
Conclusion:
Therefore, 18 men working at 10 hours a day can complete the work in 8 days.
---
- Given: 16 men work for 6 hours a day for 15 days.
- Work done by 1 man in 1 hour: Let’s denote the work done by 1 man in 1 hour as x.
- Work done by 16 men in 1 hour: 16×x=16x.
- Work done by 16 men in 6 hours (1 day):
6 hours×16x=96x
- Work done by 16 men in 15 days:
15 days×96x=1440x
Thus, the total work W is 1440x.
- Given: 18 men working for 10 hours a day.
- Work done by 18 men in 1 hour:
18×x=18x
- Work done by 18 men in 10 hours (1 day):
10 hours×18x=180x
- Work done by 18 men in T days:
T×180x
- Since this work must equal the total work W:
T×180x=1440x
- Cancel x from both sides:
T×180=1440
- Divide both sides by 180:
T=1440180
- Simplifying the fraction:
T=8
Therefore, 18 men working at 10 hours a day can complete the work in 8 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - ASSESSMENT TESTS (TEST 2)12videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - CONCEPT APPLICATION (LEVEL 3)30videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - NUMBER SYSTEMEXERCISE - ASSESSMENT TESTS24videos
NUMBER SYSTEM
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - Set theoryEXERCISE - ASSESSMENT TEST Test 212videos
Set theory
Similar Questions
Knowledge Check
- Question 1 - Select One
Twelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
A12B16C20D30 - Question 2 - Select One
Twelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?
A12B16C20D30 - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
2 men and 3 women can do a piece of work in 16 days . In how many days can 4 men and 6 women do the same work?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution