Solve the following problems :
Yogesh requires 3 days more than Vivek to do a work. If both of them work together, the work can be compleled in 2 days. Find the number of days required by each of them to complete the work.
The correct Answer is:Vivek :3 days; Yogesh :6 days.
Step by step video, text & image solution for Solve the following problems : Yogesh requires 3 days more than Vivek to do a work. If both of them work together, the work can be compleled in 2 days. Find the number of days required by each of them to complete the work. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Topper's Solved these Questions
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUADRATIC EQUATION EXERCISE - PRACTICE SET 2.117videos
QUADRATIC EQUATION
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUADRATIC EQUATION EXERCISE - PRACTICE SET 2.212videos
QUADRATIC EQUATION
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - PYTHAGORAS THEOREMEXERCISE - Challenging Questions5videos
PYTHAGORAS THEOREM
- BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUADRATIC EQUATIONS EXERCISE - ASSIGNEMENT 2.48videos
QUADRATIC EQUATIONS
Similar Questions
Rahul is twice efficient as Ram. If both of them can complete the work in 12 days. Then find the number of days Rahul would take to complete the work above.
View SolutionA and B can do a work in 15 days and 20 days respectively B started the work and they work on alternate days. Find the number of days it will take them to complete the work.
View Solution
Knowledge Check
- Question 1 - Select One
If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days - Question 2 - Select One
If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days - Question 3 - Select One
If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
A40B20C14D10
A can do a piece of work in 4 days and B can complete the same work in 12 days . What is the number of days required to do the same work together ?
View SolutionA, B and C can do a work in 20, 30 and 60 days respectively. A started the work but every third day three of them work together. Then find the number of days it too them to complete the work.
View SolutionA can do a piece of work in 4 days and B can complete the same work in 12 days. What is the number of days required to do the same work together?
View SolutionIf 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View SolutionA and B together can do a piece of work in 6 days . If A can alone do the work in 18 days then the number of days required for B to finsh the work is
View Solution