Doubtnut Promotions Sticky

Solve the following problems :
Yogesh requires 3 days more than Vivek to do a work. If both of them work together, the work can be compleled in 2 days. Find the number of days required by each of them to complete the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:Vivek :3 days; Yogesh :6 days.

|
Answer

Step by step video, text & image solution for Solve the following problems : Yogesh requires 3 days more than Vivek to do a work. If both of them work together, the work can be compleled in 2 days. Find the number of days required by each of them to complete the work. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days
  • Question 2 - Select One

    If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days
  • Question 3 - Select One

    If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

    A40
    B20
    C14
    D10